Thank you, John. I will try this out. If I have any more questions, I'll
be back.

-Mark

"John Mansfield" wrote in message
...
Mark,

Try setting your data up like this (the % Goal are the calculations you
are
looking for):

Goal % Goal
a 75,000 100%
b 60,000 80%
c 45,000 60%
d 30,000 40%
e 0 0%

Then, with the Goal numbers in column B the calculations for the % Goal
a

Goal % Goal
a 75000 1
b 60000 =B3/$B$2
c 45000 =B4/$B$2
d 30000 =B5/$B$2
e 0 =B6/$B$2

To set $75,000 at 100%, all you have to do is divide all numbers lower
than
75,000 into 75,000.

Andy Pope has some Thermometer charts at his site that can be modified to
create the chart that you want. Here's the URL:

http://www.andypope.info/charts/thermometer.htm

----
Regards,
John Mansfield
http://www.pdbook.com

"Mark" wrote:

I working on a chart to show progress towards a goal for a number of
groups,
teams, and departments. What I can' not figure out is how to, for
example,
declare $75,000 = 100%

I need to show 4 departments on a chart, each with a different goal
amount
and each goal should represent 100%.

I think that makes sense, if not, please let me know and I'll rephrase.