On Nov 21, 4:52 pm, moonhk wrote:
On 11$B7n(B21$BF|(B, $B2<8a(B3$B;~(B45$BJ,(B, carlo wrote:





Check the Help for Networkdays.


hth Carlo


On Nov 21, 4:38 pm, moonhk wrote:


Hi All


Any User using excel for Project Planning ? How can you calcuate Start
date and End date base on given Start date. The calcuation not include
Sunday and Saterday. Any Suggestion ?


Examplehttp://www.editgrid.com/user/cxleung/Planning


moonhk
GMT+8- $Bp,i6Ho0zMQJ8;z(B -


- $Bp}<(Ho0zMQJ8;z(B -


Thank a lot.- Hide quoted text -

- Show quoted text -


You're welcome, thank you for the feedback