just weekdays
No need to check for Sunday, the Saturday check will skip it
=C2+1+(WEEKDAY(C2)=6)*2
--
HTH
Bob Phillips
(replace xxxx in the email address with gmail if mailing direct)
"peter the swede" wrote in message
oups.com...
Hi all
on a spreedsheet I´ve a series with dates, where from previous date 1
day is added (i.e. C3=C2+1).
Now I wan´t to do the following:
1) check if C10 is a saturday?
2) if C10 is saturday than go to monday
3) check if C10 is sunday ?
4) if yes then add 1 day
5) if C10 is not sunday, than add 1 day
I hope you understand what I want to do
Thanks in advance
//Peter
|