Try this......

Enter the year and quarter you want the info for in two cells:

G1 = 2003
H1 = Q2

Entered as an array using the key combo of CTRL,SHIFT,ENTER:

=MIN(OFFSET(A2,MATCH(G1&H1,A2:A11&B2:B11,0),3,3))

Format the cell as TIME

This assumes the pattern of 3 batches per qtr is constant.

You'd be much better off if you stored the data in a true database style:

1 Year Quarter Date Duration of batch
2 2003 Q1 01-02-03 13:45
3 2003 Q1 02-02-03 12:45
4 2003 Q1 10-03-03 9:54
5 2003 Q2 11-04-03 11:24
6 2003 Q2 24-05-03 11:00
7 2003 Q2 24-06-03 10:15


Then you could use this array formula:

=MIN(IF(A2:A13=G1,IF(B2:B13=H1,D2:D13)))

Biff

"Mark Rugers" wrote in message
...
Hello,

I want to find the minimum time in which a batch has been produced for
each
quarter of a year. I have tried different formulas (included arrays +
Control/Shift/Enter) with unsatisfied results. Below is a simplified
example
for the year 2003.

A B C D
1 Year Quarter Date Duration of batch
2 2003 Q1 01-02-03 13:45
3 02-02-03 12:45
4 10-03-03 9:54
5 2003 Q2 11-04-03 11:24
6 24-05-03 11:00
7 24-06-03 10:15
8 2003 Q3 14-07-03 11:15
9 14-07-03 10:45
10 02-08-03 16:30
11 2003 Q4 02-11-03 15:00
12 22-11-03 12:45
13 23-12-03 13:00

I hope this makes sense.

Kind regards

Mark