That depends on your reasoning:
Networkdays includes both the start date end the end date.
so 13 and (-)21 are correct, see:
13-08-04 Fri 1
14-08-04 Sat
15-08-04 Sun
16-08-04 Mon 1
17-08-04 Tue 1
18-08-04 Wed 1
19-08-04 Thu 1
20-08-04 Fri 1
21-08-04 Sat
22-08-04 Sun
23-08-04 Mon 1
24-08-04 Tue 1
25-08-04 Wed 1
26-08-04 Thu 1
27-08-04 Fri 1
28-08-04 Sat
29-08-04 Sun
30-08-04 Mon 1
31-08-04 Tue 1 1
01-09-04 Wed 1
02-09-04 Thu 1
03-09-04 Fri 1
04-09-04 Sat
05-09-04 Sun
06-09-04 Mon 1
07-09-04 Tue 1
08-09-04 Wed 1
09-09-04 Thu 1
10-09-04 Fri 1
11-09-04 Sat
12-09-04 Sun
13-09-04 Mon 1
14-09-04 Tue 1
15-09-04 Wed 1
16-09-04 Thu 1
17-09-04 Fri 1
18-09-04 Sat
19-09-04 Sun
20-09-04 Mon 1
21-09-04 Tue 1
22-09-04 Wed 1
23-09-04 Thu 1
24-09-04 Fri 1
25-09-04 Sat
26-09-04 Sun
27-09-04 Mon 1
28-09-04 Tue 1
13 21
--
keepITcool
|
www.XLsupport.com | keepITcool chello nl | amsterdam
Patricia wrote :
Why does NETWORKDAYS add 1 to positive results and subtracts 1 from
negative results? Please see example below:
Agreed Date Actual Date Variance Calculated Should be
(Bus Days)
31/08/2004 13/08/2004 13 12
31/08/2004 28/09/2004 -21 -20
Does anyone know how to get around this? I have tried the IF
function, to no avail.