Bob,
The OP only wants to change the date if the end date falls on a weekend, not if the 10 date period
covers a weekend (which it always will).
HTH,
Bernie
MS Excel MVP
"Bob Phillips" wrote in message
...
Don't you just want to use NETWORKDAYS, it handles weekends and holidays.
--
HTH
Bob Phillips
"Randy" wrote in message
oups.com...
I need a formula that will calculate a due date 10 days from the start
date (a1)but if the date falls on a weekend or holiday I need the date
to be the next working day.
I will have a list of holidays in J2:J50.
Thanks for any help..........
|