On Fri, 7 Jan 2005 14:21:04 -0800, "hanauer"
wrote:

I want to set up a list of milestones in Excel (i.e., project starts on Day
1, writers identified on day 3, drafts due on day 10, etc.) where I can type
in the start date and have Excel fill in the dates for each milestone
automatically. If Day 3 falls on a weekend, how can I make Excel change that
result to the weekday previous to it?



=workday(A1+4,-1)

If the workday function is not available, and returns the #NAME? error, install
and load the Analysis ToolPak add-in.

On the Tools menu, click Add-Ins.
In the Add-Ins available list, select the Analysis ToolPak box, and then click
OK.
If necessary, follow the instructions in the setup program


--ron