JoAnn

Formula for adding only workdays
 
I need to have a date column that contains a date that is 3 workdays from the
date specified in another column ("date submitted").

Right now it's set to give me 3 days from the date in the submission column
but I need to have it skip weekend dates in its calculation.

Is there a way to do that?
--
JoAnn

Gord Dibben

Formula for adding only workdays
 
See help on WORKDAY function.

Note: you must load the Analysis ToolPak to make that function available.


Gord Dibben MS Excel MVP

On Mon, 11 Feb 2008 12:48:15 -0800, JoAnn
wrote:

I need to have a date column that contains a date that is 3 workdays from the
date specified in another column ("date submitted").

Right now it's set to give me 3 days from the date in the submission column
but I need to have it skip weekend dates in its calculation.

Is there a way to do that?



JoAnn

Formula for adding only workdays
 
Many thanks ... that works great!

--
JoAnn


"Gord Dibben" wrote:

See help on WORKDAY function.

Note: you must load the Analysis ToolPak to make that function available.


Gord Dibben MS Excel MVP

On Mon, 11 Feb 2008 12:48:15 -0800, JoAnn
wrote:

I need to have a date column that contains a date that is 3 workdays from the
date specified in another column ("date submitted").

Right now it's set to give me 3 days from the date in the submission column
but I need to have it skip weekend dates in its calculation.

Is there a way to do that?





All times are GMT +1. The time now is 07:48 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com