Joan

DATE ISSUE!
 
i AM ATTEMPTING TO FORCAST THE AMOUNT OF DAYS IN A SHEET, HERE'S THE EXAMPLE:
Start date Days since 100 day forcast
5-31-06 TODAY HOW DO I GET THIS???

I can the days till today but not get a date from start date plus 100 days?
I appreciate your input.

CLR

DATE ISSUE!
 
This will give you a date that is 100 days past the date in cell A2

=A2+100

Vaya con Dios,
Chuck, CABGx3





"Joan" wrote:

i AM ATTEMPTING TO FORCAST THE AMOUNT OF DAYS IN A SHEET, HERE'S THE EXAMPLE:
Start date Days since 100 day forcast
5-31-06 TODAY HOW DO I GET THIS???

I can the days till today but not get a date from start date plus 100 days?
I appreciate your input.


David Biddulph

DATE ISSUE!
 
"Joan" wrote in message
...
i AM ATTEMPTING TO FORCAST THE AMOUNT OF DAYS IN A SHEET, HERE'S THE
EXAMPLE:
Start date Days since 100 day forcast
5-31-06 TODAY HOW DO I GET
THIS???

I can the days till today but not get a date from start date plus 100
days?
I appreciate your input.


If your start date is an Excel date, rather than text, then merely add 100
to that format the result as a date.
If your 5-31-06 is text, try Data/ Text to columns
& choose date, with the DMY option. That will turn it into a date to which
you can add your 100 days.
--
David Biddulph