Chris Maximus

Adding a number to a date as workdays
 
I want to have a spreadsheet where I add a workday number to a date and get
the end date, like MS Project. What formula would I use to get the result to
show the duration as wrok days?

JE McGimpsey

Look up WORKDAY() in XL Help. It's part of the Analysis Toolpak Add-in
(Tools/Add-ins...)


In article ,
"Chris Maximus" <Chris wrote:

I want to have a spreadsheet where I add a workday number to a date and get
the end date, like MS Project. What formula would I use to get the result to
show the duration as wrok days?


Frank Kabel

Hi
use WORKDAY for this

Note: You have to install the Analysis toolpak Addin for this function

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris Maximus" <Chris schrieb im
Newsbeitrag ...
I want to have a spreadsheet where I add a workday number to a date

and get
the end date, like MS Project. What formula would I use to get the

result to
show the duration as wrok days?



Chris maximus

I guess I should have explained mo Cell a1 has date (12/01/04), cell a2
has number of work days (42), I need to add the two and get end date, where
42 will be read as workdays, and would return a date of 2/03/05 instead of
1/12/05.

"Frank Kabel" wrote:

Hi
use WORKDAY for this

Note: You have to install the Analysis toolpak Addin for this function

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris Maximus" <Chris schrieb im
Newsbeitrag ...
I want to have a spreadsheet where I add a workday number to a date

and get
the end date, like MS Project. What formula would I use to get the

result to
show the duration as wrok days?




Frank Kabel

Hi
=WORKDAY(A1,A2)

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris maximus" <Chris schrieb im
Newsbeitrag ...
I guess I should have explained mo Cell a1 has date (12/01/04),

cell a2
has number of work days (42), I need to add the two and get end date,

where
42 will be read as workdays, and would return a date of 2/03/05

instead of
1/12/05.

"Frank Kabel" wrote:

Hi
use WORKDAY for this

Note: You have to install the Analysis toolpak Addin for this

function

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris Maximus" <Chris
schrieb
im
Newsbeitrag

...
I want to have a spreadsheet where I add a workday number to a

date
and get
the end date, like MS Project. What formula would I use to get

the
result to
show the duration as wrok days?





Chris Maximus

Greetings Frankfurt!

Frank I kept trying this and it wouldn't work. But then as I was sending you
another response, I noticed the "Note: You have to install the toolpak for
this function"

Dooh!

So I installed the Analysis Toolpak, and everything is working now.

Thank you very much!!!

"Frank Kabel" wrote:

Hi
=WORKDAY(A1,A2)

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris maximus" <Chris schrieb im
Newsbeitrag ...
I guess I should have explained mo Cell a1 has date (12/01/04),

cell a2
has number of work days (42), I need to add the two and get end date,

where
42 will be read as workdays, and would return a date of 2/03/05

instead of
1/12/05.

"Frank Kabel" wrote:

Hi
use WORKDAY for this

Note: You have to install the Analysis toolpak Addin for this

function

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris Maximus" <Chris
schrieb
im
Newsbeitrag

...
I want to have a spreadsheet where I add a workday number to a

date
and get
the end date, like MS Project. What formula would I use to get

the
result to
show the duration as wrok days?





Frank Kabel

hi
glad you sorted it out ;-)

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris Maximus" <Chris schrieb im
Newsbeitrag ...
Greetings Frankfurt!

Frank I kept trying this and it wouldn't work. But then as I was

sending you
another response, I noticed the "Note: You have to install the

toolpak for
this function"

Dooh!

So I installed the Analysis Toolpak, and everything is working now.

Thank you very much!!!

"Frank Kabel" wrote:

Hi
=WORKDAY(A1,A2)

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris maximus" <Chris
schrieb
im
Newsbeitrag

...
I guess I should have explained mo Cell a1 has date

(12/01/04),
cell a2
has number of work days (42), I need to add the two and get end

date,
where
42 will be read as workdays, and would return a date of 2/03/05

instead of
1/12/05.

"Frank Kabel" wrote:

Hi
use WORKDAY for this

Note: You have to install the Analysis toolpak Addin for this

function

--
Regards
Frank Kabel
Frankfurt, Germany

"Chris Maximus" <Chris

schrieb
im
Newsbeitrag

...
I want to have a spreadsheet where I add a workday number to

a
date
and get
the end date, like MS Project. What formula would I use to

get
the
result to
show the duration as wrok days?







All times are GMT +1. The time now is 05:22 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com