Home |
Search |
Today's Posts |
#1
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
I would like to calculate the days based on three conditions. Here is the
example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#2
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Ah,
I missed the weekdays only bit, that's much more difficult. let me think!! Mike "Mike H" wrote: Hi, For this to work jan, Feb etc in row 1 must be properly formatted so enter 1/1/2009 on C1 and format as mmm to show Jan and repeat for other months Now put this formula in C2 =SUMPRODUCT((ROW(INDIRECT($A2&":"&$B2))=C$1)*(ROW (INDIRECT($A2&":"&$B2))<DATE(YEAR(C$1),MONTH(C$1)+ 1,1))) Drag down as required and then drag right as required. If one of the dates is missing you'll get a #REF! error and if this is not acceptable wrap the entire formula in an iserror statement Mike "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#3
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Hi,
For this to work jan, Feb etc in row 1 must be properly formatted so enter 1/1/2009 on C1 and format as mmm to show Jan and repeat for other months Now put this formula in C2 =SUMPRODUCT((ROW(INDIRECT($A2&":"&$B2))=C$1)*(ROW (INDIRECT($A2&":"&$B2))<DATE(YEAR(C$1),MONTH(C$1)+ 1,1))) Drag down as required and then drag right as required. If one of the dates is missing you'll get a #REF! error and if this is not acceptable wrap the entire formula in an iserror statement Mike "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#4
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Thanks for your help. It worked good on the cells have the dates. As you
stated if the one of the date is missing I got #REF!. But I don't know how do I wrap the entire formula in an iserror statement. I will aslo wait for your response on the weekday only. Thanks, Kimti "Mike H" wrote: Ah, I missed the weekdays only bit, that's much more difficult. let me think!! Mike "Mike H" wrote: Hi, For this to work jan, Feb etc in row 1 must be properly formatted so enter 1/1/2009 on C1 and format as mmm to show Jan and repeat for other months Now put this formula in C2 =SUMPRODUCT((ROW(INDIRECT($A2&":"&$B2))=C$1)*(ROW (INDIRECT($A2&":"&$B2))<DATE(YEAR(C$1),MONTH(C$1)+ 1,1))) Drag down as required and then drag right as required. If one of the dates is missing you'll get a #REF! error and if this is not acceptable wrap the entire formula in an iserror statement Mike "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#5
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Hi,
Still working on the workdays bit, this will get rid of the error =IF(COUNT($A2:$B2)=2,SUMPRODUCT((ROW(INDIRECT($A2& ":"&$B2))=C$1)*(ROW(INDIRECT($A2&":"&$B2))<DATE(Y EAR(C$1),MONTH(C$1)+1,1))),"") Mike "Kimti" wrote: Thanks for your help. It worked good on the cells have the dates. As you stated if the one of the date is missing I got #REF!. But I don't know how do I wrap the entire formula in an iserror statement. I will aslo wait for your response on the weekday only. Thanks, Kimti "Mike H" wrote: Ah, I missed the weekdays only bit, that's much more difficult. let me think!! Mike "Mike H" wrote: Hi, For this to work jan, Feb etc in row 1 must be properly formatted so enter 1/1/2009 on C1 and format as mmm to show Jan and repeat for other months Now put this formula in C2 =SUMPRODUCT((ROW(INDIRECT($A2&":"&$B2))=C$1)*(ROW (INDIRECT($A2&":"&$B2))<DATE(YEAR(C$1),MONTH(C$1)+ 1,1))) Drag down as required and then drag right as required. If one of the dates is missing you'll get a #REF! error and if this is not acceptable wrap the entire formula in an iserror statement Mike "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#6
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Try this in c2, Drag down and right as required
=MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(DATE(YEAR(C$1) ,MONTH(C$1)+1,0),$B2))) Mike "Mike H" wrote: Hi, Still working on the workdays bit, this will get rid of the error =IF(COUNT($A2:$B2)=2,SUMPRODUCT((ROW(INDIRECT($A2& ":"&$B2))=C$1)*(ROW(INDIRECT($A2&":"&$B2))<DATE(Y EAR(C$1),MONTH(C$1)+1,1))),"") Mike "Kimti" wrote: Thanks for your help. It worked good on the cells have the dates. As you stated if the one of the date is missing I got #REF!. But I don't know how do I wrap the entire formula in an iserror statement. I will aslo wait for your response on the weekday only. Thanks, Kimti "Mike H" wrote: Ah, I missed the weekdays only bit, that's much more difficult. let me think!! Mike "Mike H" wrote: Hi, For this to work jan, Feb etc in row 1 must be properly formatted so enter 1/1/2009 on C1 and format as mmm to show Jan and repeat for other months Now put this formula in C2 =SUMPRODUCT((ROW(INDIRECT($A2&":"&$B2))=C$1)*(ROW (INDIRECT($A2&":"&$B2))<DATE(YEAR(C$1),MONTH(C$1)+ 1,1))) Drag down as required and then drag right as required. If one of the dates is missing you'll get a #REF! error and if this is not acceptable wrap the entire formula in an iserror statement Mike "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#7
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Worked perfect with one exception. If B is blank, it is giving me numbers in
all the months based on date in A. Is there any way that formula can consider B as current date unless there is actual date. Thanks, Kimti "Mike H" wrote: Try this in c2, Drag down and right as required =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(DATE(YEAR(C$1) ,MONTH(C$1)+1,0),$B2))) Mike "Mike H" wrote: Hi, Still working on the workdays bit, this will get rid of the error =IF(COUNT($A2:$B2)=2,SUMPRODUCT((ROW(INDIRECT($A2& ":"&$B2))=C$1)*(ROW(INDIRECT($A2&":"&$B2))<DATE(Y EAR(C$1),MONTH(C$1)+1,1))),"") Mike "Kimti" wrote: Thanks for your help. It worked good on the cells have the dates. As you stated if the one of the date is missing I got #REF!. But I don't know how do I wrap the entire formula in an iserror statement. I will aslo wait for your response on the weekday only. Thanks, Kimti "Mike H" wrote: Ah, I missed the weekdays only bit, that's much more difficult. let me think!! Mike "Mike H" wrote: Hi, For this to work jan, Feb etc in row 1 must be properly formatted so enter 1/1/2009 on C1 and format as mmm to show Jan and repeat for other months Now put this formula in C2 =SUMPRODUCT((ROW(INDIRECT($A2&":"&$B2))=C$1)*(ROW (INDIRECT($A2&":"&$B2))<DATE(YEAR(C$1),MONTH(C$1)+ 1,1))) Drag down as required and then drag right as required. If one of the dates is missing you'll get a #REF! error and if this is not acceptable wrap the entire formula in an iserror statement Mike "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#8
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Glad that worked,
This now uses B2 or today's date =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(DATE(YEAR(C$1) ,MONTH(C$1)+1,0),MAX($B2,TODAY())))) "Kimti" wrote: Worked perfect with one exception. If B is blank, it is giving me numbers in all the months based on date in A. Is there any way that formula can consider B as current date unless there is actual date. Thanks, Kimti "Mike H" wrote: Try this in c2, Drag down and right as required =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(DATE(YEAR(C$1) ,MONTH(C$1)+1,0),$B2))) Mike "Mike H" wrote: Hi, Still working on the workdays bit, this will get rid of the error =IF(COUNT($A2:$B2)=2,SUMPRODUCT((ROW(INDIRECT($A2& ":"&$B2))=C$1)*(ROW(INDIRECT($A2&":"&$B2))<DATE(Y EAR(C$1),MONTH(C$1)+1,1))),"") Mike "Kimti" wrote: Thanks for your help. It worked good on the cells have the dates. As you stated if the one of the date is missing I got #REF!. But I don't know how do I wrap the entire formula in an iserror statement. I will aslo wait for your response on the weekday only. Thanks, Kimti "Mike H" wrote: Ah, I missed the weekdays only bit, that's much more difficult. let me think!! Mike "Mike H" wrote: Hi, For this to work jan, Feb etc in row 1 must be properly formatted so enter 1/1/2009 on C1 and format as mmm to show Jan and repeat for other months Now put this formula in C2 =SUMPRODUCT((ROW(INDIRECT($A2&":"&$B2))=C$1)*(ROW (INDIRECT($A2&":"&$B2))<DATE(YEAR(C$1),MONTH(C$1)+ 1,1))) Drag down as required and then drag right as required. If one of the dates is missing you'll get a #REF! error and if this is not acceptable wrap the entire formula in an iserror statement Mike "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#9
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
...MAX($B2,TODAY()))))
If B2 is not empty and is less than today and C1 then you get incorrect results. This seems to work: =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(C$1+31-DAY(C$1+31),IF($B2="",NOW(),$B2)))) -- Biff Microsoft Excel MVP "Mike H" wrote in message ... Glad that worked, This now uses B2 or today's date =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(DATE(YEAR(C$1) ,MONTH(C$1)+1,0),MAX($B2,TODAY())))) "Kimti" wrote: Worked perfect with one exception. If B is blank, it is giving me numbers in all the months based on date in A. Is there any way that formula can consider B as current date unless there is actual date. Thanks, Kimti "Mike H" wrote: Try this in c2, Drag down and right as required =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(DATE(YEAR(C$1) ,MONTH(C$1)+1,0),$B2))) Mike "Mike H" wrote: Hi, Still working on the workdays bit, this will get rid of the error =IF(COUNT($A2:$B2)=2,SUMPRODUCT((ROW(INDIRECT($A2& ":"&$B2))=C$1)*(ROW(INDIRECT($A2&":"&$B2))<DATE(Y EAR(C$1),MONTH(C$1)+1,1))),"") Mike "Kimti" wrote: Thanks for your help. It worked good on the cells have the dates. As you stated if the one of the date is missing I got #REF!. But I don't know how do I wrap the entire formula in an iserror statement. I will aslo wait for your response on the weekday only. Thanks, Kimti "Mike H" wrote: Ah, I missed the weekdays only bit, that's much more difficult. let me think!! Mike "Mike H" wrote: Hi, For this to work jan, Feb etc in row 1 must be properly formatted so enter 1/1/2009 on C1 and format as mmm to show Jan and repeat for other months Now put this formula in C2 =SUMPRODUCT((ROW(INDIRECT($A2&":"&$B2))=C$1)*(ROW (INDIRECT($A2&":"&$B2))<DATE(YEAR(C$1),MONTH(C$1)+ 1,1))) Drag down as required and then drag right as required. If one of the dates is missing you'll get a #REF! error and if this is not acceptable wrap the entire formula in an iserror statement Mike "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#10
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
If you are expecitng the below results...try the below formula which uses
WEEKDAY() Start date finish date 1/1/2009 2/1/2009 3/1/2009 3-Jan-09 27-Jan-09 17 0 0 24-Feb-09 0 4 22 25-Feb-09 12-Mar-09 0 3 9 =MAX(0,SUM(INT((WEEKDAY(MAX(C$1,$A2)-{1,2,3,4,5},2)+MIN(IF($B2="",TODAY(),$B2),DATE(YEA R(C$1),MONTH(C$1)+1,0))-MAX(C$1,$A2))/7))) If this post helps click Yes --------------- Jacob Skaria "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
#11
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Just thought of something...
Since we're already using an ATP function**, NETWORKDAYS, we can replace C$1+31-DAY(C$1+31) with the EOMONTH function. Saves a couple of keystrokes and reduces the total calculations. =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(EOMONTH(C$1,0) ,IF($B2="",NOW(),$B2)))) ** This formula requires the Analysis ToolPak add-in be installed for Excel versions prior to Excel 2007. -- Biff Microsoft Excel MVP "T. Valko" wrote in message ... ...MAX($B2,TODAY())))) If B2 is not empty and is less than today and C1 then you get incorrect results. This seems to work: =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(C$1+31-DAY(C$1+31),IF($B2="",NOW(),$B2)))) -- Biff Microsoft Excel MVP "Mike H" wrote in message ... Glad that worked, This now uses B2 or today's date =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(DATE(YEAR(C$1) ,MONTH(C$1)+1,0),MAX($B2,TODAY())))) "Kimti" wrote: Worked perfect with one exception. If B is blank, it is giving me numbers in all the months based on date in A. Is there any way that formula can consider B as current date unless there is actual date. Thanks, Kimti "Mike H" wrote: Try this in c2, Drag down and right as required =MAX(0,NETWORKDAYS(MAX(C$1,$A2),MIN(DATE(YEAR(C$1) ,MONTH(C$1)+1,0),$B2))) Mike "Mike H" wrote: Hi, Still working on the workdays bit, this will get rid of the error =IF(COUNT($A2:$B2)=2,SUMPRODUCT((ROW(INDIRECT($A2& ":"&$B2))=C$1)*(ROW(INDIRECT($A2&":"&$B2))<DATE(Y EAR(C$1),MONTH(C$1)+1,1))),"") Mike "Kimti" wrote: Thanks for your help. It worked good on the cells have the dates. As you stated if the one of the date is missing I got #REF!. But I don't know how do I wrap the entire formula in an iserror statement. I will aslo wait for your response on the weekday only. Thanks, Kimti "Mike H" wrote: Ah, I missed the weekdays only bit, that's much more difficult. let me think!! Mike "Mike H" wrote: Hi, For this to work jan, Feb etc in row 1 must be properly formatted so enter 1/1/2009 on C1 and format as mmm to show Jan and repeat for other months Now put this formula in C2 =SUMPRODUCT((ROW(INDIRECT($A2&":"&$B2))=C$1)*(ROW (INDIRECT($A2&":"&$B2))<DATE(YEAR(C$1),MONTH(C$1)+ 1,1))) Drag down as required and then drag right as required. If one of the dates is missing you'll get a #REF! error and if this is not acceptable wrap the entire formula in an iserror statement Mike "Kimti" wrote: I would like to calculate the days based on three conditions. Here is the example of my work sheet: A B C D E F 1 Start date finish date Jan Feb Mar April 2 Jan 03, 2009 Jan 27, 2009 3 Feb 24, 2009 4 Feb 25, 2009 Mar 12, 2009 I want see the days caclulated by month for any task started. If task goes to next month, days should go to next month column and I want to calculate the weekdays only. As above row 3 date in column A is start date of task and task is not complete and we are in April. I want to see the days in for Feb in D3 and days in Mar in E3. Once I show task complete, calculation should end in April in F3. I hope this is clear explanation. Thank you in advance for your help. Kimti |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Conditional Formatting Dates calculating 10 days and 30 days from a certain date | Excel Worksheet Functions | |||
Calculation of working days between two dates | Excel Worksheet Functions | |||
Dates calculation using working days | Excel Discussion (Misc queries) | |||
Please Help With Days Elapsed And Days Remaining Calculation | Excel Worksheet Functions | |||
Calculation to determine days between two dates | Excel Worksheet Functions |