![]() |
Date calculation help please!
Hello,
I am trying to find a formula to calculation the estimated completion date for different operations which returns the date excluding holiday working 7 days a week @ 19 hours per day, but couldn't seemed to find the answer how. Column A1 is the startdate. Column B is the production time in days required to completed. Column C starting C3 is the calculated value of completion date in date time format. Here is the sample table: A B C 1/2/2009 6:00 AM StartDate Opr ProdTime (Days) ComplDate 10 2.045 1/6/09 1:04 AM 20 0.143 30 0.667 40 1.611 50 0.667 Thank for sugguestions |
Date calculation help please!
This gives you the result you posted
=WORKDAY($A$1,INT(B3))+MOD(B3,1) but I don't get why it is 01:04 AM and not 07:04 AM. How does 19 hours factor in, what are the 5 non-working hours? -- __________________________________ HTH Bob "Cam" wrote in message ... Hello, I am trying to find a formula to calculation the estimated completion date for different operations which returns the date excluding holiday working 7 days a week @ 19 hours per day, but couldn't seemed to find the answer how. Column A1 is the startdate. Column B is the production time in days required to completed. Column C starting C3 is the calculated value of completion date in date time format. Here is the sample table: A B C 1/2/2009 6:00 AM StartDate Opr ProdTime (Days) ComplDate 10 2.045 1/6/09 1:04 AM 20 0.143 30 0.667 40 1.611 50 0.667 Thank for sugguestions |
Date calculation help please!
Hi
The returns the same answer as Bob but uses the 19 hour factor =A1+SUM(B2:B6)/24*19 Where the start date is in A1 and the days are in B2:B6. To handle holidays you will need to modify the approach: =C3-NETWORKDAYS(A1,C3,M1:M5)+NETWORKDAYS(A1,C3) In this case the first formula is in C3 and you would enter Holidays in M1:M5 -- If this helps, please click the Yes button Cheers, Shane Devenshire "Cam" wrote: Hello, I am trying to find a formula to calculation the estimated completion date for different operations which returns the date excluding holiday working 7 days a week @ 19 hours per day, but couldn't seemed to find the answer how. Column A1 is the startdate. Column B is the production time in days required to completed. Column C starting C3 is the calculated value of completion date in date time format. Here is the sample table: A B C 1/2/2009 6:00 AM StartDate Opr ProdTime (Days) ComplDate 10 2.045 1/6/09 1:04 AM 20 0.143 30 0.667 40 1.611 50 0.667 Thank for sugguestions |
Date calculation help please!
Thanks Shane & Bob,
I will try out the formula tomorrow. Was ask to do another item which is to calculation the date return per shift. There are shift, 1st & 2nd shift is 6.5 and 3rd shift is 6 hrs. Do I use the same formula except /24*6.5 for 1 & 2 and /24*6 for 3 shift? Result wanted: 1/2/2009 6:00 AM StartDate Opr ProdTime (Days) 1st shift 2nd shift 3rd shift 10 2.045 " " 1/6/09 1:04 AM 20 0.143 30 0.667 40 1.611 50 0.667 "Shane Devenshire" wrote: Hi The returns the same answer as Bob but uses the 19 hour factor =A1+SUM(B2:B6)/24*19 Where the start date is in A1 and the days are in B2:B6. To handle holidays you will need to modify the approach: =C3-NETWORKDAYS(A1,C3,M1:M5)+NETWORKDAYS(A1,C3) In this case the first formula is in C3 and you would enter Holidays in M1:M5 -- If this helps, please click the Yes button Cheers, Shane Devenshire "Cam" wrote: Hello, I am trying to find a formula to calculation the estimated completion date for different operations which returns the date excluding holiday working 7 days a week @ 19 hours per day, but couldn't seemed to find the answer how. Column A1 is the startdate. Column B is the production time in days required to completed. Column C starting C3 is the calculated value of completion date in date time format. Here is the sample table: A B C 1/2/2009 6:00 AM StartDate Opr ProdTime (Days) ComplDate 10 2.045 1/6/09 1:04 AM 20 0.143 30 0.667 40 1.611 50 0.667 Thank for sugguestions |
Date calculation help please!
Bob,
The formula is working except it doesn't exclude holiday. I have a separate sheet called Holidays with a list of all the holidays in date. How can I incorporate it into the formula to exclude those holidays? big thanks. "Bob Phillips" wrote: This gives you the result you posted =WORKDAY($A$1,INT(B3))+MOD(B3,1) but I don't get why it is 01:04 AM and not 07:04 AM. How does 19 hours factor in, what are the 5 non-working hours? -- __________________________________ HTH Bob "Cam" wrote in message ... Hello, I am trying to find a formula to calculation the estimated completion date for different operations which returns the date excluding holiday working 7 days a week @ 19 hours per day, but couldn't seemed to find the answer how. Column A1 is the startdate. Column B is the production time in days required to completed. Column C starting C3 is the calculated value of completion date in date time format. Here is the sample table: A B C 1/2/2009 6:00 AM StartDate Opr ProdTime (Days) ComplDate 10 2.045 1/6/09 1:04 AM 20 0.143 30 0.667 40 1.611 50 0.667 Thank for sugguestions |
Date calculation help please!
=WORKDAY($A$1,INT(B3),holiday_range)+MOD(B3,1)
-- __________________________________ HTH Bob "Cam" wrote in message ... Bob, The formula is working except it doesn't exclude holiday. I have a separate sheet called Holidays with a list of all the holidays in date. How can I incorporate it into the formula to exclude those holidays? big thanks. "Bob Phillips" wrote: This gives you the result you posted =WORKDAY($A$1,INT(B3))+MOD(B3,1) but I don't get why it is 01:04 AM and not 07:04 AM. How does 19 hours factor in, what are the 5 non-working hours? -- __________________________________ HTH Bob "Cam" wrote in message ... Hello, I am trying to find a formula to calculation the estimated completion date for different operations which returns the date excluding holiday working 7 days a week @ 19 hours per day, but couldn't seemed to find the answer how. Column A1 is the startdate. Column B is the production time in days required to completed. Column C starting C3 is the calculated value of completion date in date time format. Here is the sample table: A B C 1/2/2009 6:00 AM StartDate Opr ProdTime (Days) ComplDate 10 2.045 1/6/09 1:04 AM 20 0.143 30 0.667 40 1.611 50 0.667 Thank for sugguestions |
Date calculation help please!
Bob,
Thanks, I included the holiday range (in date format), but I don't know why it is still counting those holidays as workday. My calendar holiday is not normal US holidays, but I thought it shouldn't matter if it is based on the holiday list I specified. Any ideal? "Bob Phillips" wrote: =WORKDAY($A$1,INT(B3),holiday_range)+MOD(B3,1) -- __________________________________ HTH Bob "Cam" wrote in message ... Bob, The formula is working except it doesn't exclude holiday. I have a separate sheet called Holidays with a list of all the holidays in date. How can I incorporate it into the formula to exclude those holidays? big thanks. "Bob Phillips" wrote: This gives you the result you posted =WORKDAY($A$1,INT(B3))+MOD(B3,1) but I don't get why it is 01:04 AM and not 07:04 AM. How does 19 hours factor in, what are the 5 non-working hours? -- __________________________________ HTH Bob "Cam" wrote in message ... Hello, I am trying to find a formula to calculation the estimated completion date for different operations which returns the date excluding holiday working 7 days a week @ 19 hours per day, but couldn't seemed to find the answer how. Column A1 is the startdate. Column B is the production time in days required to completed. Column C starting C3 is the calculated value of completion date in date time format. Here is the sample table: A B C 1/2/2009 6:00 AM StartDate Opr ProdTime (Days) ComplDate 10 2.045 1/6/09 1:04 AM 20 0.143 30 0.667 40 1.611 50 0.667 Thank for sugguestions |
Date calculation help please!
I picked up in your new thread.
-- __________________________________ HTH Bob "Cam" wrote in message ... Bob, Thanks, I included the holiday range (in date format), but I don't know why it is still counting those holidays as workday. My calendar holiday is not normal US holidays, but I thought it shouldn't matter if it is based on the holiday list I specified. Any ideal? "Bob Phillips" wrote: =WORKDAY($A$1,INT(B3),holiday_range)+MOD(B3,1) -- __________________________________ HTH Bob "Cam" wrote in message ... Bob, The formula is working except it doesn't exclude holiday. I have a separate sheet called Holidays with a list of all the holidays in date. How can I incorporate it into the formula to exclude those holidays? big thanks. "Bob Phillips" wrote: This gives you the result you posted =WORKDAY($A$1,INT(B3))+MOD(B3,1) but I don't get why it is 01:04 AM and not 07:04 AM. How does 19 hours factor in, what are the 5 non-working hours? -- __________________________________ HTH Bob "Cam" wrote in message ... Hello, I am trying to find a formula to calculation the estimated completion date for different operations which returns the date excluding holiday working 7 days a week @ 19 hours per day, but couldn't seemed to find the answer how. Column A1 is the startdate. Column B is the production time in days required to completed. Column C starting C3 is the calculated value of completion date in date time format. Here is the sample table: A B C 1/2/2009 6:00 AM StartDate Opr ProdTime (Days) ComplDate 10 2.045 1/6/09 1:04 AM 20 0.143 30 0.667 40 1.611 50 0.667 Thank for sugguestions |
All times are GMT +1. The time now is 11:39 PM. |
Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com