![]() |
Using workday function to populate schedule
Hi,
I wonder if anyone can help. Using the workday formula and conditional formatting Ive created a Gantt chart in Excel that behaves more or less like a Project file. I have one small problem. The WORKDAY function looks like this: =WORKDAY(D5,F5,C1:D1:E1:F1:G1:H1:I1:J1)-1 The -1 at the end of the formula is there to solve a problem with the Gantt chart. The WORKDAY function adds the number of days the task lasts (cell F5 in this case) to the start date (D5). So if you enter a duration of 5 days into F5, you end up with six shaded cells on the Gantt chart; hence the -1. However, for some reason with the -1 in the formula, a job that the formula thinks ends on a Monday is shown as ending on a Sunday. So for instance: Start date (D5) €“ 02/12/2008 (a Tuesday) Duration in days (F5) €“ 4 End date (using above formula) €“ 07/12/2008 (a Sunday) So, my question: am I using the WORKDAY function incorrectly? Why doesnt it show the job ending the formula minus one working day (Friday 5 December, which is when the task really does end)? Is there a better way of getting the WORKDAY function to include the start date as part of the duration of the task? And I know I could just enter a duration thats one day shorter than it really is, but I want everyone on our project to be able to use this. I dont always want to be left wondering if a ten-step project is actually ten days too long or too short. Many thanks for any help and advice you can give. Best regards Karl |
Using workday function to populate schedule
Hi Karl,
<Why doesnt it show the job ending the formula minus one working day Because the -1 is ourside of the WORFDAY() function.... Use =WORKDAY(D5,F5-1,C1:D1:E1:F1:G1:H1:I1:J1), which, I think, is equivalent to =WORKDAY(D5,F5-1,C1:J1) instead -- Kind regards, Niek Otten Microsoft MVP - Excel "Karl" wrote in message ... Hi, I wonder if anyone can help. Using the workday formula and conditional formatting Ive created a Gantt chart in Excel that behaves more or less like a Project file. I have one small problem. The WORKDAY function looks like this: =WORKDAY(D5,F5,C1:D1:E1:F1:G1:H1:I1:J1)-1 The -1 at the end of the formula is there to solve a problem with the Gantt chart. The WORKDAY function adds the number of days the task lasts (cell F5 in this case) to the start date (D5). So if you enter a duration of 5 days into F5, you end up with six shaded cells on the Gantt chart; hence the -1. However, for some reason with the -1 in the formula, a job that the formula thinks ends on a Monday is shown as ending on a Sunday. So for instance: Start date (D5) €“ 02/12/2008 (a Tuesday) Duration in days (F5) €“ 4 End date (using above formula) €“ 07/12/2008 (a Sunday) So, my question: am I using the WORKDAY function incorrectly? Why doesnt it show the job ending the formula minus one working day (Friday 5 December, which is when the task really does end)? Is there a better way of getting the WORKDAY function to include the start date as part of the duration of the task? And I know I could just enter a duration thats one day shorter than it really is, but I want everyone on our project to be able to use this. I dont always want to be left wondering if a ten-step project is actually ten days too long or too short. Many thanks for any help and advice you can give. Best regards Karl |
Using workday function to populate schedule
Hi Niek,
Thanks for that; it works perfectly. One more question, is there a way of adding only workdays to the value of a cell. so for instance: D6 = E5 + 1 working day I'm now trying to avoid having tasks starting on the weekend. Thanks Karl "Niek Otten" wrote: Hi Karl, <Why doesnt it show the job ending the formula minus one working day Because the -1 is ourside of the WORFDAY() function.... Use =WORKDAY(D5,F5-1,C1:D1:E1:F1:G1:H1:I1:J1), which, I think, is equivalent to =WORKDAY(D5,F5-1,C1:J1) instead -- Kind regards, Niek Otten Microsoft MVP - Excel "Karl" wrote in message ... Hi, I wonder if anyone can help. Using the workday formula and conditional formatting Ive created a Gantt chart in Excel that behaves more or less like a Project file. I have one small problem. The WORKDAY function looks like this: =WORKDAY(D5,F5,C1:D1:E1:F1:G1:H1:I1:J1)-1 The -1 at the end of the formula is there to solve a problem with the Gantt chart. The WORKDAY function adds the number of days the task lasts (cell F5 in this case) to the start date (D5). So if you enter a duration of 5 days into F5, you end up with six shaded cells on the Gantt chart; hence the -1. However, for some reason with the -1 in the formula, a job that the formula thinks ends on a Monday is shown as ending on a Sunday. So for instance: Start date (D5) €“ 02/12/2008 (a Tuesday) Duration in days (F5) €“ 4 End date (using above formula) €“ 07/12/2008 (a Sunday) So, my question: am I using the WORKDAY function incorrectly? Why doesnt it show the job ending the formula minus one working day (Friday 5 December, which is when the task really does end)? Is there a better way of getting the WORKDAY function to include the start date as part of the duration of the task? And I know I could just enter a duration thats one day shorter than it really is, but I want everyone on our project to be able to use this. I dont always want to be left wondering if a ten-step project is actually ten days too long or too short. Many thanks for any help and advice you can give. Best regards Karl |
All times are GMT +1. The time now is 03:59 AM. |
Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com