If you enter DATE(2008,10,1) as the Start_date and 10/1/08 as the End_date it
shows a difference of N=1 workday. Which means the system is subtracting
39722 from 39722 and getting a total of 1.

If you enter DATE(2008,11,1 ) as the Start_date and 11/1/08 as the End_date
it shows a difference of N=0 workdays. Which means the system is correctly
subtracting 39753 from 39753 and getting a total of 0.

What is causing the difference when the same formula is used? Is this a
glitch in the system?
 
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
networkday - datedif BNT1 via OfficeKB.com New Users to Excel 5 April 8th 08 07:32 PM
6 day/week function ie:networkday Robert Excel Worksheet Functions 6 August 6th 07 12:06 AM
Businessday (Networkday) Function dannyboy213 Excel Discussion (Misc queries) 4 February 2nd 06 12:30 AM
Networkday Calendar rac Excel Discussion (Misc queries) 2 January 22nd 06 01:27 PM
NETWORKDAY function problem - starting on weekends [email protected] Excel Discussion (Misc queries) 5 June 16th 05 10:55 PM


All times are GMT +1. The time now is 01:28 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"