PLEASE HELP URGENT
I need to be able to predict a date of completion through a percent completed
over a year, please, please help!!! |
PLEASE HELP URGENT
Is your prediction based on linear progress (i.e., if you're halfway
done, it will take twice the total elapsed time)? or some other function? A linear solution: A1: <start date A2: <% completed A3: =A1 + (TODAY()-A1)/A2 In article , Frontier wrote: I need to be able to predict a date of completion through a percent completed over a year, please, please help!!! |