need help with networkdays formula
want to setup formula using networkdays through which end date which is 30
workingdays from start date can be calculated. |
need help with networkdays formula
With a start date in A1 try this:-
=WORKDAY(A1,30,C1:C8) C1 - C8 are a list of public holidays. This argument is optional soo you could use. =WORKDAY(A1,30) Mike "aashishtaneja" wrote: want to setup formula using networkdays through which end date which is 30 workingdays from start date can be calculated. |