Calculation of working days between two dates
I am trying to calculate the difference between one cell and another - both having dates in, to establish if a service level is being achieved for completing a task. eg. B2 = 25/6/07 and L2 = 30/6/07 (5 days) currently if there is no date in L2, it will say "open call" - indicating that it has not been completed. the calculation used currently is =IF(ISERROR(DAYS360(B2,L2,TRUE)),"Open Call",DAYS360(B2,L2,TRUE)) however this does not show working days taken to complete the call, which is key to the measurement. have tried advice below, but unfortunately it still includes the weekend days - can I include the WEEKDAYS or NETWORKDAYS formula in this somehow? thanks "Mike H" wrote: Andy, Try this:- =IF(L2="","Open Call",L2-B2) Format as general. It assumes L2 will always be a later date then B2 or blank. Mike |
Calculation of working days between two dates
Andy,
=IF(L2="", "Open Call",NETWORKDAYS(B2,L2)) HTH, Bernie MS Excel MVP "Andy B" wrote in message ... I am trying to calculate the difference between one cell and another - both having dates in, to establish if a service level is being achieved for completing a task. eg. B2 = 25/6/07 and L2 = 30/6/07 (5 days) currently if there is no date in L2, it will say "open call" - indicating that it has not been completed. the calculation used currently is =IF(ISERROR(DAYS360(B2,L2,TRUE)),"Open Call",DAYS360(B2,L2,TRUE)) however this does not show working days taken to complete the call, which is key to the measurement. have tried advice below, but unfortunately it still includes the weekend days - can I include the WEEKDAYS or NETWORKDAYS formula in this somehow? thanks "Mike H" wrote: Andy, Try this:- =IF(L2="","Open Call",L2-B2) Format as general. It assumes L2 will always be a later date then B2 or blank. Mike |
All times are GMT +1. The time now is 08:37 PM. |
Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com