I have a spread sheet used for production planning which predicts the finsh time of a job depending on its duration. This works fine but I now have the problem that production is no longer 24 hours so if a 12 hour job starts at 15:00, no work will be done between 21:00 and 06:00 (9 hours) so it will finish at 12:00 noon on the following day.
Is there a formula that will add 9 hours to the duration if the calculated finish time falls during the night shift? Thanks in anticipation Martin |
calculate finishing time if night shift aren't working
If your start time is in A2, duration in B2, night shift start time in C$2, night shift finish time in D$2:
Finish time would be =A2+B2+IF(A2+B2C$2,MOD(D$2-C$2,1)) -- David Biddulph "Martin B" wrote in message ... I have a spread sheet used for production planning which predicts the finsh time of a job depending on its duration. This works fine but I now have the problem that production is no longer 24 hours so if a 12 hour job starts at 15:00, no work will be done between 21:00 and 06:00 (9 hours) so it will finish at 12:00 noon on the following day. Is there a formula that will add 9 hours to the duration if the calculated finish time falls during the night shift? Thanks in anticipation Martin |
All times are GMT +1. The time now is 10:34 AM. |
Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com