I have a user who would like to calculate a date going 60 working days
forward from a date in her spreadsheet. One column contains the date of an
incident and she needs a date 60 working days ahead when the report of the
incident is due. Only working days, not total days.
She currently counts the days manually. Anyone have a solution for her?
--
Donna

Teethless mama

Date going forward
 
=WORKDAY(A1,60)

Format cells as date


"Donna" wrote:

I have a user who would like to calculate a date going 60 working days
forward from a date in her spreadsheet. One column contains the date of an
incident and she needs a date 60 working days ahead when the report of the
incident is due. Only working days, not total days.
She currently counts the days manually. Anyone have a solution for her?
--
Donna


David Biddulph[_2_]

Date going forward
 
=WORKDAY(A1,60)
--
David Biddulph

"Donna" wrote in message
...
I have a user who would like to calculate a date going 60 working days
forward from a date in her spreadsheet. One column contains the date of
an
incident and she needs a date 60 working days ahead when the report of the
incident is due. Only working days, not total days.
She currently counts the days manually. Anyone have a solution for her?
--
Donna





All times are GMT +1. The time now is 05:07 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com