Weekend
I'm trying to schedule a product through up to 4 operations. We do not
operate on Friday, Saturday and Sunday. The product has do be made the day before it is delivered. Question; if I have to deliver a product on 06/04/07 (Monday). Is there a way to calculate the final aoperation to the previous Thursday? It needs to acknowledge Sunday, Saturday, Friday, and Holidays and schedule the operation for Thursday. Thanks in advance Geo |
Weekend
Hi,
You want to use the WORKDAY(StartDate,Days,Holidays) function. To use this function you must attach the Analysis ToolPak. Tools, Add-in. Create a range that contains all Fridays and any other Holidays and highlight that range for the Holidays argument of the function. The Days argument can be negative. -- Cheers, Shane Devenshire "Pass Codes" wrote: I'm trying to schedule a product through up to 4 operations. We do not operate on Friday, Saturday and Sunday. The product has do be made the day before it is delivered. Question; if I have to deliver a product on 06/04/07 (Monday). Is there a way to calculate the final aoperation to the previous Thursday? It needs to acknowledge Sunday, Saturday, Friday, and Holidays and schedule the operation for Thursday. Thanks in advance Geo |
Weekend
A1: delivery date
=IF(WEEKDAY(WORKDAY(A1,-1,holidays),2)<5,WORKDAY(A1,-1,holidays),WORKDAY(A1,-2,holidays)) "Pass Codes" wrote: I'm trying to schedule a product through up to 4 operations. We do not operate on Friday, Saturday and Sunday. The product has do be made the day before it is delivered. Question; if I have to deliver a product on 06/04/07 (Monday). Is there a way to calculate the final aoperation to the previous Thursday? It needs to acknowledge Sunday, Saturday, Friday, and Holidays and schedule the operation for Thursday. Thanks in advance Geo |
All times are GMT +1. The time now is 10:35 AM. |
Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com