NETWORKDAYS calculation returns inconsistent results
I'm using NETWORKDAYS in a scheduling spreadsheet to calculate the
number of working days between two date columns. The first column (C) records the date a task was created, the second (E) when the task is scheduled to be completed. If the lead time (the difference between these dates) is less than 3 working days, I want to flag the fact. The calculation IF(NETWORKDAYS(C258,E258)<3,"x","") works most of the time, but occasionally there are instances whe a) there are actually 3 clear working days between the dates but the above formula returns "x" and b) there are less than 3 clear working days between the dates but the above formula does NOT return "x" Am I missing some subtlety of the function here? |
NETWORKDAYS calculation returns inconsistent results
On 29 Aug 2006 17:00:23 -0700, "Analowl" wrote:
I'm using NETWORKDAYS in a scheduling spreadsheet to calculate the number of working days between two date columns. The first column (C) records the date a task was created, the second (E) when the task is scheduled to be completed. If the lead time (the difference between these dates) is less than 3 working days, I want to flag the fact. The calculation IF(NETWORKDAYS(C258,E258)<3,"x","") works most of the time, but occasionally there are instances whe a) there are actually 3 clear working days between the dates but the above formula returns "x" and b) there are less than 3 clear working days between the dates but the above formula does NOT return "x" Am I missing some subtlety of the function here? Post some examples of the data you are using, the actual results, and the expected results. --ron |
All times are GMT +1. The time now is 07:05 PM. |
Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com