ExcelBanter

ExcelBanter (https://www.excelbanter.com/)
-   Excel Worksheet Functions (https://www.excelbanter.com/excel-worksheet-functions/)
-   -   NETWORKDAYS calc with 3 columns of dates (https://www.excelbanter.com/excel-worksheet-functions/104407-networkdays-calc-3-columns-dates.html)

Mendz5

NETWORKDAYS calc with 3 columns of dates
 
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the result in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the result in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the result in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it that way,
lucky me.

Thanks,

Mendz

Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the result

in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the result

in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the result

in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it that way,
lucky me.

Thanks,

Mendz




Mark

NETWORKDAYS calc with 3 columns of dates
 

Mendz5 wrote:
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the result in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the result in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the result in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it that way,
lucky me.

Thanks,

Mendz


1. If A1 is blank, but B1 & C1 are populated, I want to put the
result in
D1.

What do you mean by the result? I cant help you if I don't understand
what you want in the cell


Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

The formula almost works, unless I fat fingered something, which is entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter what I put in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the result

in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the result

in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the result

in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it that way,
lucky me.

Thanks,

Mendz





Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Mark,

Sorry about that. I want the result to be the total number of workdays
between the given dates.

Thanks,

Mendz

"Mark" wrote:


Mendz5 wrote:
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the result in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the result in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the result in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it that way,
lucky me.

Thanks,

Mendz


1. If A1 is blank, but B1 & C1 are populated, I want to put the
result in
D1.

What do you mean by the result? I cant help you if I don't understand
what you want in the cell



Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
Mendz,

No it was my error on the second part. This corrects the always 1 problem

=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so didn't cater for it.
What do you want to happen if they are all present as NETWORKDAYS only works
on 2 dates. If you want earliest to latets then perhaps,

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something, which is

entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter what I put

in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:


=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the

result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the

result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the

result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it that

way,
lucky me.

Thanks,

Mendz







Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

Thank you so much, the formula works perfectly. I know the basic functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the always 1 problem

=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so didn't cater for it.
What do you want to happen if they are all present as NETWORKDAYS only works
on 2 dates. If you want earliest to latets then perhaps,

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something, which is

entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter what I put

in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:


=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the

result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the

result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the

result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it that

way,
lucky me.

Thanks,

Mendz







Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of them, so I get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C, depending upon
whether the first chosen is A or B (for instance if A is completed, then the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case I don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the basic

functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the always 1

problem


=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so didn't cater for

it.
What do you want to happen if they are all present as NETWORKDAYS only

works
on 2 dates. If you want earliest to latets then perhaps,

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something, which is

entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter what I

put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:



=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the

result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the

result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the

result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it

that
way,
lucky me.

Thanks,

Mendz









Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

Thank you very much for the explanation. When you break it up like that, it
makes it so much clearer.

Thanks again,

Mendz

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of them, so I get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C, depending upon
whether the first chosen is A or B (for instance if A is completed, then the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case I don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the basic

functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the always 1

problem


=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so didn't cater for

it.
What do you want to happen if they are all present as NETWORKDAYS only

works
on 2 dates. If you want earliest to latets then perhaps,

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something, which is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter what I

put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:



=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it

that
way,
lucky me.

Thanks,

Mendz










Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the target cell

If 2 or more cells are populated, then I want to put the number of days in
the target cell

I think I can create a formula if all cells are populated, but I'm having
trouble figuring out how to exclude 1 or more cells that are blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of them, so I get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C, depending upon
whether the first chosen is A or B (for instance if A is completed, then the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case I don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the basic

functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the always 1

problem


=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so didn't cater for

it.
What do you want to happen if they are all present as NETWORKDAYS only

works
on 2 dates. If you want earliest to latets then perhaps,

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something, which is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter what I

put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:



=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want it

that
way,
lucky me.

Thanks,

Mendz










Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the target cell

If 2 or more cells are populated, then I want to put the number of days in
the target cell

I think I can create a formula if all cells are populated, but I'm having
trouble figuring out how to exclude 1 or more cells that are blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of them, so I

get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C, depending upon
whether the first chosen is A or B (for instance if A is completed, then

the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case I don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the basic

functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the always 1

problem



=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so didn't cater

for
it.
What do you want to happen if they are all present as NETWORKDAYS

only
works
on 2 dates. If you want earliest to latets then perhaps,

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something, which

is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter

what I
put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:




=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put

the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put

the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put

the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want

it
that
way,
lucky me.

Thanks,

Mendz












Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

After entering the formula a green flag appeared in the cell and states that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the target cell

If 2 or more cells are populated, then I want to put the number of days in
the target cell

I think I can create a formula if all cells are populated, but I'm having
trouble figuring out how to exclude 1 or more cells that are blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of them, so I

get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C, depending upon
whether the first chosen is A or B (for instance if A is completed, then

the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case I don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the always 1
problem



=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so didn't cater

for
it.
What do you want to happen if they are all present as NETWORKDAYS

only
works
on 2 dates. If you want earliest to latets then perhaps,

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something, which

is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter

what I
put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:




=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to put

the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to put

the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to put

the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be want

it
that
way,
lucky me.

Thanks,

Mendz













Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
I don't know, I don't have Excel 2003 so I don't know what a green flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the cell and states

that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the target

cell

If 2 or more cells are populated, then I want to put the number of

days in
the target cell

I think I can create a formula if all cells are populated, but I'm

having
trouble figuring out how to exclude 1 or more cells that are blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of them, so

I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C, depending

upon
whether the first chosen is A or B (for instance if A is completed,

then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case I

don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the always

1
problem




=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so didn't

cater
for
it.
What do you want to happen if they are all present as

NETWORKDAYS
only
works
on 2 dates. If you want earliest to latets then perhaps,

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something,

which
is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter

what I
put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:





=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to

put
the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to

put
the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to

put
the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be

want
it
that
way,
lucky me.

Thanks,

Mendz















Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

In 2003 when excel thinks there is an error it puts a little green triangle
in the upper left corner of the cell. When you click on the flag, a drop
down appears with several options. At the top of the drop down it states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest and the
lastest dates and plugged them into one of the formulas that I know work and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a green flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the cell and states

that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the target

cell

If 2 or more cells are populated, then I want to put the number of

days in
the target cell

I think I can create a formula if all cells are populated, but I'm

having
trouble figuring out how to exclude 1 or more cells that are blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of them, so

I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C, depending

upon
whether the first chosen is A or B (for instance if A is completed,

then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case I

don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the always

1
problem




=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so didn't

cater
for
it.
What do you want to happen if they are all present as

NETWORKDAYS
only
works
on 2 dates. If you want earliest to latets then perhaps,

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something,

which
is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no matter
what I
put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:





=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing
direct)

"Mendz5" wrote in message
...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want to

put
the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want to

put
the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want to

put
the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that be

want
it
that
way,
lucky me.

Thanks,

Mendz
















Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula in adjacent cells
seem to follow a pattern, and the formula in that cell does not match the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a little green

triangle
in the upper left corner of the cell. When you click on the flag, a drop
down appears with several options. At the top of the drop down it states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest and the
lastest dates and plugged them into one of the formulas that I know work

and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a green flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the cell and

states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the

target
cell

If 2 or more cells are populated, then I want to put the number of

days in
the target cell

I think I can create a formula if all cells are populated, but I'm

having
trouble figuring out how to exclude 1 or more cells that are

blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and

latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of

them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C,

depending
upon
whether the first chosen is A or B (for instance if A is

completed,
then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case

I
don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the

basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the

always
1
problem





=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so

didn't
cater
for
it.
What do you want to happen if they are all present as

NETWORKDAYS
only
works
on 2 dates. If you want earliest to latets then perhaps,


=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",

ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something,

which
is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no

matter
what I
put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:






=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want

to
put
the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want

to
put
the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want

to
put
the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that

be
want
it
that
way,
lucky me.

Thanks,

Mendz


















Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

Thanks, you've been a great help!!

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula in adjacent cells
seem to follow a pattern, and the formula in that cell does not match the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a little green

triangle
in the upper left corner of the cell. When you click on the flag, a drop
down appears with several options. At the top of the drop down it states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest and the
lastest dates and plugged them into one of the formulas that I know work

and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a green flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the cell and

states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the

target
cell

If 2 or more cells are populated, then I want to put the number of
days in
the target cell

I think I can create a formula if all cells are populated, but I'm
having
trouble figuring out how to exclude 1 or more cells that are

blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and

latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of

them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C,

depending
upon
whether the first chosen is A or B (for instance if A is

completed,
then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case

I
don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the

basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the

always
1
problem





=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so

didn't
cater
for
it.
What do you want to happen if they are all present as
NETWORKDAYS
only
works
on 2 dates. If you want earliest to latets then perhaps,


=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",

ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing
direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something,
which
is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no

matter
what I
put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:






=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want

to
put
the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want

to
put
the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want

to
put
the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that

be
want
it
that
way,


Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

I'm back again. After looking at the results of the most recent formula, I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and ending date, for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that should be counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the above results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to the above
results.

Of course, if any one of the sets only has 1 date, then that set should not
be included.

Here is what I have coded:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MIN(J2:K2) ,MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETWORKDAYS( MIN(M2:N2),MAX(M2:N2))+IF(COUNTIF(Q2:R2,"<")=2,NE TWORKDAYS(MIN(Q2:R2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE" in the target
cell

If the second or third set of cells is missing one date, the formula only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula in adjacent cells
seem to follow a pattern, and the formula in that cell does not match the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a little green

triangle
in the upper left corner of the cell. When you click on the flag, a drop
down appears with several options. At the top of the drop down it states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest and the
lastest dates and plugged them into one of the formulas that I know work

and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a green flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the cell and

states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the

target
cell

If 2 or more cells are populated, then I want to put the number of
days in
the target cell

I think I can create a formula if all cells are populated, but I'm
having
trouble figuring out how to exclude 1 or more cells that are

blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and

latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of

them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C,

depending
upon
whether the first chosen is A or B (for instance if A is

completed,
then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in case

I
don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know the

basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the

always
1
problem





=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so

didn't
cater
for
it.
What do you want to happen if they are all present as
NETWORKDAYS
only
works
on 2 dates. If you want earliest to latets then perhaps,


=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",

ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing
direct)

"Mendz5" wrote in message
...
Bob,

The formula almost works, unless I fat fingered something,
which
is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are added.

When B1 & C1 are popluated the result is always "1", no

matter
what I
put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:






=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I want

to
put
the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I want

to
put
the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I want

to
put
the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in D1.

5. If A1 & C1 are blank, I want to put "N/A" in D1.

6. If B1 & C1 are blank, I want to put "N/A" in D1.

Why are there 3 date fields you ask, the powers that

be
want
it
that
way,


Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most recent formula,

I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and ending date,

for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that should be counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the above

results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to the above
results.

Of course, if any one of the sets only has 1 date, then that set should

not
be included.

Here is what I have coded:


=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI
N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:
N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE" in the target
cell

If the second or third set of cells is missing one date, the formula only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula in adjacent

cells
seem to follow a pattern, and the formula in that cell does not match

the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a little green

triangle
in the upper left corner of the cell. When you click on the flag, a

drop
down appears with several options. At the top of the drop down it

states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest and the
lastest dates and plugged them into one of the formulas that I know

work
and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a green

flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the cell and

states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the

target
cell

If 2 or more cells are populated, then I want to put the

number of
days in
the target cell

I think I can create a formula if all cells are populated, but

I'm
having
trouble figuring out how to exclude 1 or more cells that are

blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and

latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of

them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C,

depending
upon
whether the first chosen is A or B (for instance if A is

completed,
then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in

case
I
don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know

the
basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the

always
1
problem






=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so

didn't
cater
for
it.
What do you want to happen if they are all present as
NETWORKDAYS
only
works
on 2 dates. If you want earliest to latets then perhaps,


=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",

ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

The formula almost works, unless I fat fingered

something,
which
is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.

When A1, B1 & C1 are populated, only A1 & B1 are

added.

When B1 & C1 are popluated the result is always "1",

no
matter
what I
put
in
C1.

Thanks,

Mendz

"Bob Phillips" wrote:







=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(B1<"",B
1,C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
I have 3 columns of dates (A1, B1, C1).
Several different scenarios:

1. If A1 is blank, but B1 & C1 are populated, I

want
to
put
the
result
in
D1.

2. If B1 is blank, but A1 & C1 are populated, I

want
to
put
the
result
in
D1.

3. If C1 is blank, but A1 & B1 are populated, I

want
to
put
the
result
in
D1.

4. If A1 & B1 are blank, I want to put "N/A" in

D1.

5. If A1 & C1 are blank, I want to put "N/A" in

D1.

6. If B1 & C1 are blank, I want to put "N/A" in

D1.

Why are there 3 date fields you ask, the powers

that
be
want
it
that
way,




Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

Thanks again! What did adding the ABS and the zero at the end of each
NETWORKDAYS function do? I'm just trying to understand the logic, so that I
can use it in the future.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most recent formula,

I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and ending date,

for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that should be counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the above

results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to the above
results.

Of course, if any one of the sets only has 1 date, then that set should

not
be included.

Here is what I have coded:


=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI
N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:
N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE" in the target
cell

If the second or third set of cells is missing one date, the formula only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula in adjacent

cells
seem to follow a pattern, and the formula in that cell does not match

the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a little green
triangle
in the upper left corner of the cell. When you click on the flag, a

drop
down appears with several options. At the top of the drop down it

states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest and the
lastest dates and plugged them into one of the formulas that I know

work
and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a green

flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the cell and
states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in the
target
cell

If 2 or more cells are populated, then I want to put the

number of
days in
the target cell

I think I can create a formula if all cells are populated, but

I'm
having
trouble figuring out how to exclude 1 or more cells that are
blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1)) and
latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one of
them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or C,
depending
upon
whether the first chosen is A or B (for instance if A is
completed,
then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it in

case
I
don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing
direct)

"Mendz5" wrote in message
...
Bob,

Thank you so much, the formula works perfectly. I know

the
basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects the
always
1
problem






=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition, so
didn't
cater
for
it.
What do you want to happen if they are all present as
NETWORKDAYS
only
works
on 2 dates. If you want earliest to latets then perhaps,


=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",

ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

The formula almost works, unless I fat fingered

something,
which
is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.


Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
The ABS is just so that I don't have to worry whether the first date is
earlier or later than the second, saves testing for it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thanks again! What did adding the ABS and the zero at the end of each
NETWORKDAYS function do? I'm just trying to understand the logic, so that

I
can use it in the future.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most recent

formula,
I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and ending

date,
for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that should be

counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the above

results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to the above
results.

Of course, if any one of the sets only has 1 date, then that set

should
not
be included.

Here is what I have coded:



=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI

N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:
N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE" in the

target
cell

If the second or third set of cells is missing one date, the formula

only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula in

adjacent
cells
seem to follow a pattern, and the formula in that cell does not

match
the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a little green
triangle
in the upper left corner of the cell. When you click on the flag,

a
drop
down appears with several options. At the top of the drop down it

states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest and

the
lastest dates and plugged them into one of the formulas that I

know
work
and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a

green
flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the cell

and
states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",

ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in

the
target
cell

If 2 or more cells are populated, then I want to put the

number of
days in
the target cell

I think I can create a formula if all cells are populated,

but
I'm
having
trouble figuring out how to exclude 1 or more cells that

are
blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1))

and
latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one

of
them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or

C,
depending
upon
whether the first chosen is A or B (for instance if A is
completed,
then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it

in
case
I
don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

Thank you so much, the formula works perfectly. I

know
the
basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects

the
always
1
problem







=IF(COUNTIF(A1:C1,"<")<2,"N/A",ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1=""
,B1=""),C1,B1))))

I though A1 and B1 and C1 was not a valid condition,

so
didn't
cater
for
it.
What do you want to happen if they are all present

as
NETWORKDAYS
only
works
on 2 dates. If you want earliest to latets then

perhaps,


=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",

ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

The formula almost works, unless I fat fingered

something,
which
is
entirely
possible (I'll double check again).

When A1 & B1 are populated the calculation works.

When A1 & C1 are populated the calculation works.




Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

Sorry to be a pest, but what does the zero do?

Mendz

"Bob Phillips" wrote:

The ABS is just so that I don't have to worry whether the first date is
earlier or later than the second, saves testing for it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thanks again! What did adding the ABS and the zero at the end of each
NETWORKDAYS function do? I'm just trying to understand the logic, so that

I
can use it in the future.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most recent

formula,
I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and ending

date,
for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that should be

counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the above
results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to the above
results.

Of course, if any one of the sets only has 1 date, then that set

should
not
be included.

Here is what I have coded:



=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI

N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:
N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE" in the

target
cell

If the second or third set of cells is missing one date, the formula

only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula in

adjacent
cells
seem to follow a pattern, and the formula in that cell does not

match
the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a little green
triangle
in the upper left corner of the cell. When you click on the flag,

a
drop
down appears with several options. At the top of the drop down it
states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest and

the
lastest dates and plugged them into one of the formulas that I

know
work
and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a

green
flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the cell

and
states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",

ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing
direct)

"Mendz5" wrote in message
...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A" in

the
target
cell

If 2 or more cells are populated, then I want to put the
number of
days in
the target cell

I think I can create a formula if all cells are populated,

but
I'm
having
trouble figuring out how to exclude 1 or more cells that

are
blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest (MIN(A1:C1))

and
latest
(MAX(A1:C1)) dates and calculate the difference using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be one

of
them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B) or

C,
depending
upon
whether the first chosen is A or B (for instance if A is
completed,
then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and ABS it

in
case
I
don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

Thank you so much, the formula works perfectly. I

know
the
basic
functions
of excel, could you explain the formula you created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This corrects

the


Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
Adds 0 if both dates are not present.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Sorry to be a pest, but what does the zero do?

Mendz

"Bob Phillips" wrote:

The ABS is just so that I don't have to worry whether the first date is
earlier or later than the second, saves testing for it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thanks again! What did adding the ABS and the zero at the end of each
NETWORKDAYS function do? I'm just trying to understand the logic, so

that
I
can use it in the future.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most recent

formula,
I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and ending

date,
for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that should be

counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the

above
results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to the

above
results.

Of course, if any one of the sets only has 1 date, then that set

should
not
be included.

Here is what I have coded:




=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI


N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:
N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE" in

the
target
cell

If the second or third set of cells is missing one date, the

formula
only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula in

adjacent
cells
seem to follow a pattern, and the formula in that cell does not

match
the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a little

green
triangle
in the upper left corner of the cell. When you click on the

flag,
a
drop
down appears with several options. At the top of the drop

down it
states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest

and
the
lastest dates and plugged them into one of the formulas that I

know
work
and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a

green
flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the

cell
and
states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",

ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A"

in
the
target
cell

If 2 or more cells are populated, then I want to put

the
number of
days in
the target cell

I think I can create a formula if all cells are

populated,
but
I'm
having
trouble figuring out how to exclude 1 or more cells

that
are
blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest

(MIN(A1:C1))
and
latest
(MAX(A1:C1)) dates and calculate the difference

using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be

one
of
them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B)

or
C,
depending
upon
whether the first chosen is A or B (for instance if

A is
completed,
then
the
second date must be B or C). The formula for this is

IF(OR(A1="",B1=""),C1,B1)

I pass the two selected dates to NETWORKSDAYS and

ABS it
in
case
I
don't
pass them in date order.

That's it.


--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

Thank you so much, the formula works perfectly. I

know
the
basic
functions
of excel, could you explain the formula you

created.

Thanks,

Mendz

"Bob Phillips" wrote:

Mendz,

No it was my error on the second part. This

corrects
the




Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

Now the boss doesn't want the first day of the range to count. This was the
first formula you gave me with the 3 columns:

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

I think a "+1" has to be added but I'm not sure where in the formula to
place it.

Thanks,

Mendz

"Bob Phillips" wrote:

Adds 0 if both dates are not present.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Sorry to be a pest, but what does the zero do?

Mendz

"Bob Phillips" wrote:

The ABS is just so that I don't have to worry whether the first date is
earlier or later than the second, saves testing for it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thanks again! What did adding the ABS and the zero at the end of each
NETWORKDAYS function do? I'm just trying to understand the logic, so

that
I
can use it in the future.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most recent
formula,
I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and ending
date,
for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that should be
counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the

above
results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to the

above
results.

Of course, if any one of the sets only has 1 date, then that set
should
not
be included.

Here is what I have coded:




=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI


N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:
N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE" in

the
target
cell

If the second or third set of cells is missing one date, the

formula
only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula in
adjacent
cells
seem to follow a pattern, and the formula in that cell does not
match
the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a little

green
triangle
in the upper left corner of the cell. When you click on the

flag,
a
drop
down appears with several options. At the top of the drop

down it
states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the earliest

and
the
lastest dates and plugged them into one of the formulas that I
know
work
and
received the same results.

So thanks again! This discussion group has been a great help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know what a
green
flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing
direct)

"Mendz5" wrote in message
...
Bob,

After entering the formula a green flag appeared in the

cell
and
states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",

ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put "N/A"

in
the
target
cell

If 2 or more cells are populated, then I want to put

the
number of
days in
the target cell

I think I can create a formula if all cells are

populated,
but
I'm
having
trouble figuring out how to exclude 1 or more cells

that
are
blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest

(MIN(A1:C1))
and
latest
(MAX(A1:C1)) dates and calculate the difference

using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B must be

one
of
them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or B)

or
C,
depending
upon
whether the first chosen is A or B (for instance if

A is
completed,
then
the
second date must be B or C). The formula for this is


Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
You mean that if there are 3 dates, he wants the difference between the
second and the third?

BTW, this all seems odd, what is it for?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Now the boss doesn't want the first day of the range to count. This was

the
first formula you gave me with the 3 columns:

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

I think a "+1" has to be added but I'm not sure where in the formula to
place it.

Thanks,

Mendz

"Bob Phillips" wrote:

Adds 0 if both dates are not present.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Sorry to be a pest, but what does the zero do?

Mendz

"Bob Phillips" wrote:

The ABS is just so that I don't have to worry whether the first date

is
earlier or later than the second, saves testing for it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thanks again! What did adding the ABS and the zero at the end of

each
NETWORKDAYS function do? I'm just trying to understand the logic,

so
that
I
can use it in the future.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most

recent
formula,
I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and

ending
date,
for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that

should be
counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the

above
results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to

the
above
results.

Of course, if any one of the sets only has 1 date, then that

set
should
not
be included.

Here is what I have coded:





=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI



N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:

N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE"

in
the
target
cell

If the second or third set of cells is missing one date, the

formula
only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula

in
adjacent
cells
seem to follow a pattern, and the formula in that cell does

not
match
the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a

little
green
triangle
in the upper left corner of the cell. When you click on

the
flag,
a
drop
down appears with several options. At the top of the drop

down it
states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the

earliest
and
the
lastest dates and plugged them into one of the formulas

that I
know
work
and
received the same results.

So thanks again! This discussion group has been a great

help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know

what a
green
flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

After entering the formula a green flag appeared in

the
cell
and
states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",

ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put

"N/A"
in
the
target
cell

If 2 or more cells are populated, then I want to

put
the
number of
days in
the target cell

I think I can create a formula if all cells are

populated,
but
I'm
having
trouble figuring out how to exclude 1 or more

cells
that
are
blank.

Thanks,

Mendz

If t

"Bob Phillips" wrote:

Ok.

First, I check if all 3 cells are completed

COUNTIF(A1:C1,"<")=3

If this is true, I determine the earliest

(MIN(A1:C1))
and
latest
(MAX(A1:C1)) dates and calculate the difference

using

NETWORKDAYS(MIN(A1:C1),MAX(A1:C1))

If they are not all completed I check if any two

are

COUNTIF(A1:C1,"<")<2

and if so error with "N/A"

If any two are completed, then either A or B

must be
one
of
them, so
I
get
the first date with

IF(A1<"",A1,B1)

then I determine the second date as either (A or

B)
or
C,
depending
upon
whether the first chosen is A or B (for instance

if
A is
completed,
then
the
second date must be B or C). The formula for

this is




Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

No,

If A1 = 7/06/06, B1 = 7/11/06 and C1 = 7/13/06

He wants to begin counting with A1 plus 1 day

If A1 is blank, B1 = 7/11/06 and C1 = 7/13/06

he wants to use B1 + 1 day

If A1 = 7/06/06, B1 is blank and C1 = 7/13/06

He wants to begin counting with A1 plus 1 day

We have a process where project documents are shuffled from one group to
another and he wants to know the duration of time that the documents spend in
each group. Some dates we have, some dates are just not available, that's
why some of the cells can be blank.

Essentially, he has to justify why some projects are being delayed.

Thanks,

Mendz

"Bob Phillips" wrote:

You mean that if there are 3 dates, he wants the difference between the
second and the third?

BTW, this all seems odd, what is it for?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Now the boss doesn't want the first day of the range to count. This was

the
first formula you gave me with the 3 columns:

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

I think a "+1" has to be added but I'm not sure where in the formula to
place it.

Thanks,

Mendz

"Bob Phillips" wrote:

Adds 0 if both dates are not present.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Sorry to be a pest, but what does the zero do?

Mendz

"Bob Phillips" wrote:

The ABS is just so that I don't have to worry whether the first date

is
earlier or later than the second, saves testing for it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thanks again! What did adding the ABS and the zero at the end of

each
NETWORKDAYS function do? I'm just trying to understand the logic,

so
that
I
can use it in the future.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most

recent
formula,
I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and

ending
date,
for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that

should be
counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the
above
results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to

the
above
results.

Of course, if any one of the sets only has 1 date, then that

set
should
not
be included.

Here is what I have coded:





=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI



N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:

N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE"

in
the
target
cell

If the second or third set of cells is missing one date, the
formula
only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula

in
adjacent
cells
seem to follow a pattern, and the formula in that cell does

not
match
the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing
direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a

little
green
triangle
in the upper left corner of the cell. When you click on

the
flag,
a
drop
down appears with several options. At the top of the drop
down it
states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the

earliest
and
the
lastest dates and plugged them into one of the formulas

that I
know
work
and
received the same results.

So thanks again! This discussion group has been a great

help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know

what a
green
flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

After entering the formula a green flag appeared in

the
cell
and
states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",

ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if
mailing
direct)

"Mendz5" wrote in
message

...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put

"N/A"
in
the
target
cell

If 2 or more cells are populated, then I want to

put
the
number of
days in
the target cell

I think I can create a formula if all cells are


Mendz5

NETWORKDAYS calc with 3 columns of dates
 
Bob,

Forgot to mention the following:

If A1 and B1 are the same date and C1 is blank, then the result should be 1
day duration.

The same goes if A1, B1 and C1 are the same date the result should be 1 day
duration.

If A1 and C1 are the same date and B1 is blank, the result should be 1 day
duration.

And finally, If B1 and C1 are the same date and A1 is blank the result
should be 1 day duration.

Sorry for this mess :-(

Thank,

Mendz

"Bob Phillips" wrote:

You mean that if there are 3 dates, he wants the difference between the
second and the third?

BTW, this all seems odd, what is it for?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Now the boss doesn't want the first day of the range to count. This was

the
first formula you gave me with the 3 columns:

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

I think a "+1" has to be added but I'm not sure where in the formula to
place it.

Thanks,

Mendz

"Bob Phillips" wrote:

Adds 0 if both dates are not present.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Sorry to be a pest, but what does the zero do?

Mendz

"Bob Phillips" wrote:

The ABS is just so that I don't have to worry whether the first date

is
earlier or later than the second, saves testing for it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Thanks again! What did adding the ABS and the zero at the end of

each
NETWORKDAYS function do? I'm just trying to understand the logic,

so
that
I
can use it in the future.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most

recent
formula,
I
realized that I didn't explain properly what I needed, sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning and

ending
date,
for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that

should be
counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to the
above
results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added to

the
above
results.

Of course, if any one of the sets only has 1 date, then that

set
should
not
be included.

Here is what I have coded:





=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI



N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:

N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a "FALSE"

in
the
target
cell

If the second or third set of cells is missing one date, the
formula
only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the formula

in
adjacent
cells
seem to follow a pattern, and the formula in that cell does

not
match
the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing
direct)

"Mendz5" wrote in message
...
Bob,

In 2003 when excel thinks there is an error it puts a

little
green
triangle
in the upper left corner of the cell. When you click on

the
flag,
a
drop
down appears with several options. At the top of the drop
down it
states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the

earliest
and
the
lastest dates and plugged them into one of the formulas

that I
know
work
and
received the same results.

So thanks again! This discussion group has been a great

help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't know

what a
green
flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

After entering the formula a green flag appeared in

the
cell
and
states
that
the the formula is inconsistent. Should I ignore it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",

ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if
mailing
direct)

"Mendz5" wrote in
message

...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to put

"N/A"
in
the
target
cell

If 2 or more cells are populated, then I want to

put
the
number of
days in
the target cell

I think I can create a formula if all cells are


Bob Phillips

NETWORKDAYS calc with 3 columns of dates
 
=IF(COUNTIF(A1:C1,"<")<2,"N/A",IF(MIN(A1:C1)=MAX(A1:C1),1,NETWORKDAYS(MIN(A
1:C1)+1,MAX(A1:C1))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Forgot to mention the following:

If A1 and B1 are the same date and C1 is blank, then the result should be

1
day duration.

The same goes if A1, B1 and C1 are the same date the result should be 1

day
duration.

If A1 and C1 are the same date and B1 is blank, the result should be 1 day
duration.

And finally, If B1 and C1 are the same date and A1 is blank the result
should be 1 day duration.

Sorry for this mess :-(

Thank,

Mendz

"Bob Phillips" wrote:

You mean that if there are 3 dates, he wants the difference between the
second and the third?

BTW, this all seems odd, what is it for?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Now the boss doesn't want the first day of the range to count. This

was
the
first formula you gave me with the 3 columns:

=IF(COUNTIF(A1:C1,"<")=3,NETWORKDAYS(MIN(A1:C1),M AX(A1:C1)),
IF(COUNTIF(A1:C1,"<")<2,"N/A",
ABS(NETWORKDAYS(IF(A1<"",A1,B1),IF(OR(A1="",B1="" ),C1,B1)))))

I think a "+1" has to be added but I'm not sure where in the formula

to
place it.

Thanks,

Mendz

"Bob Phillips" wrote:

Adds 0 if both dates are not present.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing direct)

"Mendz5" wrote in message
...
Bob,

Sorry to be a pest, but what does the zero do?

Mendz

"Bob Phillips" wrote:

The ABS is just so that I don't have to worry whether the first

date
is
earlier or later than the second, saves testing for it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

Thanks again! What did adding the ABS and the zero at the end

of
each
NETWORKDAYS function do? I'm just trying to understand the

logic,
so
that
I
can use it in the future.

Thanks,

Mendz

"Bob Phillips" wrote:

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",
IF(COUNTIF(J2:K2,"<")=2,ABS(NETWORKDAYS(J2,K2)),0 )+
IF(COUNTIF(M2:N2,"<")=2,ABS(NETWORKDAYS(M2,N2)),0 )+
IF(COUNTIF(Q2:R2,"<")=2,ABS(NETWORKDAYS(Q2,R2)),0 ))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if mailing

direct)

"Mendz5" wrote in message
...
Bob,

I'm back again. After looking at the results of the most

recent
formula,
I
realized that I didn't explain properly what I needed,

sorry.

Anyway, here it is:

There are 3 sets of 2 columns, each set has a beginning

and
ending
date,
for
example:

J2 - 7/26/06 and K2 8/4/06 that is the networkdays that

should be
counted

M2 - 8/8/06 and N2 8/9/06 this duration should be added to

the
above
results

Q2 - 8/14/06 and R2 8/16/06 this duration should be added

to
the
above
results.

Of course, if any one of the sets only has 1 date, then

that
set
should
not
be included.

Here is what I have coded:






=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",IF(COUNTIF(J2:K2,"<")=2,NETWORKDAYS(MI




N(J2:K2),MAX(J2:K2))+IF(COUNTIF(M2:N2,"<")=2,NETW ORKDAYS(MIN(M2:N2),MAX(M2:

N2))+IF(COUNTIF(Q2:R2,"<")=2,NETWORKDAYS(MIN(Q2:R 2),MAX(Q2:R2))))))

If all cells are populated, then the formula works.

If the first set of cells is missing 1 date, I get a

"FALSE"
in
the
target
cell

If the second or third set of cells is missing one date,

the
formula
only
returns the duration of the first set of cells.


Thanks,

Mendz

"Bob Phillips" wrote:

I wonder what inconsistent formula actually means?

Just looked it up and apparently it means that the

formula
in
adjacent
cells
seem to follow a pattern, and the formula in that cell

does
not
match
the
formula.

So it seems reasonable to just ignore it.

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

In 2003 when excel thinks there is an error it puts a

little
green
triangle
in the upper left corner of the cell. When you click

on
the
flag,
a
drop
down appears with several options. At the top of the

drop
down it
states
inconsistent formula. I selected ignore error.

The formula does appear to work properly. I took the

earliest
and
the
lastest dates and plugged them into one of the

formulas
that I
know
work
and
received the same results.

So thanks again! This discussion group has been a

great
help.

Mendz

"Bob Phillips" wrote:

I don't know, I don't have Excel 2003 so I don't

know
what a
green
flag
actually means. Do you get the correct answer?

--
HTH

Bob Phillips

(replace somewhere in email address with gmail if

mailing
direct)

"Mendz5" wrote in

message

...
Bob,

After entering the formula a green flag appeared

in
the
cell
and
states
that
the the formula is inconsistent. Should I ignore

it?

Mendz

"Bob Phillips" wrote:

Hi Mendz,

I have found a better solution

=IF(COUNT(J2:K2,M2:N2,Q2:R2)<2,"N/A",

ABS(NETWORKDAYS(MIN(J2:K2,M2:N2,Q2:R2),MAX(J2:K2,M 2:N2,Q2:R2))))

--
HTH

Bob Phillips

(replace somewhere in email address with gmail

if
mailing
direct)

"Mendz5"

wrote in
message

...
Bob,

I'm back with something even more complex:

6 columns, but they are not next to each

other.

J2, K2, M2, N2, Q2, R2

If only 1 cell is populated, then I want to

put
"N/A"
in
the
target
cell

If 2 or more cells are populated, then I want

to
put
the
number of
days in
the target cell

I think I can create a formula if all cells

are




All times are GMT +1. The time now is 01:53 AM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com