![]() |
Removing Weekends From a Formula...
OK, so, I have the following data:
Batch Start Date and Time - 10/12/08 14:00 Batch Finish Date and Time - 15/12/08 16:55 Batch Duration - =SUM(B2-A2) Which supplies me with the answer: 5.12 However, we shut down over the weekend, so I need to remove the weekend from the answer, which would give me 3.12. Trying to do this using Networkdays doesn't seem to include the hours, so I just get the answer 4, as it touched 4 working days. Anyone know of something that could help me? Thanks in advance! Lee |
Removing Weekends From a Formula...
Hi,
Try this =(NETWORKDAYS(A2,B2)-1)+MOD(B2,1)-MOD(A2,1) Firmkat as number to 2 decimal places. Note that if you want this formula will acceot the Holidays argument =(NETWORKDAYS(A2,B2,Holidays)-1)+MOD(B2,1)-MOD(A2,1) Mike " wrote: OK, so, I have the following data: Batch Start Date and Time - 10/12/08 14:00 Batch Finish Date and Time - 15/12/08 16:55 Batch Duration - =SUM(B2-A2) Which supplies me with the answer: 5.12 However, we shut down over the weekend, so I need to remove the weekend from the answer, which would give me 3.12. Trying to do this using Networkdays doesn't seem to include the hours, so I just get the answer 4, as it touched 4 working days. Anyone know of something that could help me? Thanks in advance! Lee |
Removing Weekends From a Formula...
try:
=IF(WEEKNUM(B2)WEEKNUM(A2),B2-A2-2,B2-A2) On 10 Gru, 12:54, wrote: OK, so, I have the following data: Batch Start Date and Time - 10/12/08 14:00 Batch Finish Date and Time - 15/12/08 16:55 Batch Duration - =SUM(B2-A2) Which supplies me with the answer: 5.12 However, we shut down over the weekend, so I need to remove the weekend from the answer, which would give me 3.12. Trying to do this using Networkdays doesn't seem to include the hours, so I just get the answer 4, as it touched 4 working days. Anyone know of something that could help me? Thanks in advance! Lee |
Removing Weekends From a Formula...
The Networkdays function is part of the analysis tool pack. Be sure that is
installed or else you will get an error. " wrote: OK, so, I have the following data: Batch Start Date and Time - 10/12/08 14:00 Batch Finish Date and Time - 15/12/08 16:55 Batch Duration - =SUM(B2-A2) Which supplies me with the answer: 5.12 However, we shut down over the weekend, so I need to remove the weekend from the answer, which would give me 3.12. Trying to do this using Networkdays doesn't seem to include the hours, so I just get the answer 4, as it touched 4 working days. Anyone know of something that could help me? Thanks in advance! Lee |
All times are GMT +1. The time now is 07:36 AM. |
Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com