Need to calculate future date based on standard duration and input
Hi, I work in a development organization and we take our products through
various "stages"... here are the variables: 1) We start at Stage 1 and Stage 5 means 'ready to ship' 2) We have 3 different product classifications, A, B, C 3) Each classification has a 'standard duration' from various Stages to Stage 5 (i.e. Stage 1 to Stage 5 for a Class A is 18 months, Stage 2 to Stage 5 for a Class A is 12 months, Stage 1 to Stage 5 for a Class C is 12 months, etc.... I have a big table in Excel, each Row contains 1 product and lists the product Class, Stage 1 scheduled date, Stage 1 Actual date, Stage 2 date, Stage 3 date, Stage 4 date I need to calculate for each product at any given time the expected Stage 5 date based on the standard duration from the last Stage passed (or the Stage 1 scheduled date for pre Stage 1 products). I cannot do this in Excel with a formula because there are too many nested "if" statements... so I'm searching for a way to do this with VBA... Any help? thanks! Jon |
Need to calculate future date based on standard duration andinput
On Apr 11, 11:20*am, Jonathan Horvath
wrote: Hi, I work in a development organization and we take our products through various "stages"... here are the variables: 1) We start at Stage 1 and Stage 5 means 'ready to ship' 2) We have 3 different product classifications, A, B, C 3) Each classification has a 'standard duration' from various Stages to Stage 5 (i.e. Stage 1 to Stage 5 for a Class A is 18 months, Stage 2 to Stage 5 for a Class A is 12 months, Stage 1 to Stage 5 for a Class C is 12 months, etc.... I have a big table in Excel, each Row contains 1 product and lists the product Class, Stage 1 scheduled date, Stage 1 Actual date, Stage 2 date, Stage 3 date, Stage 4 date I need to calculate for each product at any given time the expected Stage 5 date based on the standard duration from the last Stage passed (or the Stage 1 scheduled date for pre Stage 1 products). I cannot do this in Excel with a formula because there are too many nested "if" statements... so I'm searching for a way to do this with VBA... Any help? thanks! Jon To avoid nested ifs, build a table somewhere, listing all the different permutations of classes, start stage, and end stage ... and use vlookups. That should work, I think.. Chris |
Need to calculate future date based on standard duration and i
That woud work, but I have a couple of additional constraints I forgot to
manage, I'm responding to you and Steve here... 1) I need to do this in Excel so I can share it with others 2) I need to avoid using vlookups because not everyone has those installed in Excel - and have you ever tried to get an Executive to do something in Excel other than open a file and start screaming ??? :) Jon "cht13er" wrote: On Apr 11, 11:20 am, Jonathan Horvath wrote: Hi, I work in a development organization and we take our products through various "stages"... here are the variables: 1) We start at Stage 1 and Stage 5 means 'ready to ship' 2) We have 3 different product classifications, A, B, C 3) Each classification has a 'standard duration' from various Stages to Stage 5 (i.e. Stage 1 to Stage 5 for a Class A is 18 months, Stage 2 to Stage 5 for a Class A is 12 months, Stage 1 to Stage 5 for a Class C is 12 months, etc.... I have a big table in Excel, each Row contains 1 product and lists the product Class, Stage 1 scheduled date, Stage 1 Actual date, Stage 2 date, Stage 3 date, Stage 4 date I need to calculate for each product at any given time the expected Stage 5 date based on the standard duration from the last Stage passed (or the Stage 1 scheduled date for pre Stage 1 products). I cannot do this in Excel with a formula because there are too many nested "if" statements... so I'm searching for a way to do this with VBA... Any help? thanks! Jon To avoid nested ifs, build a table somewhere, listing all the different permutations of classes, start stage, and end stage ... and use vlookups. That should work, I think.. Chris |