In an excel project scheduling under one sheet (WYSIWYG : amount, qty, days :
back-up with Auditing tools and Circular Pop-ups ) and trying to avoid bounty
windows of MS Project (very hard to re-audit) and due to records
availability.....I hope excel users can help me with my job task now....

Here's the 1st phase question..A DATE PROBLEM...

PROBLEM :
what formula to fill-in for my 100 activity list.
FOR EACH ACTIVITY
UPDATE START DATE: on A7
UPDATE FINISH DATE: on B7
UPDATE DURATION: on C7 : as effective days

I have data available for one item

ORIG. START DATE : on A5 = 02-Oct-06
ORIG. FINISH DATE : on B5 = 02-Nov-02
ORIG DURATION : on C5 = B5-A5+1 = 397 days.

OUR DEFINED NAMES WITH DATA AVAILABLE TO COVER THE WHOLE SCHEDULING:
MO2 = M1:CV1 (contains the 1st date of each month ;e.g. 1-Sep-06, 1-Nov-10)
......M1= 01-Jan-06
MF2 = M2:CV2 (contains the 1st date of each month ;e.g. 30-Sep-06, 30-Nov-10)
......M2= 31-Jan-06
DPM2 = M3:CV3 (contains the number of calendar days in each month above)
......M3= 31
RDPM2 = M4:CV4 (contains the project actual number of effective days in each
month above)
......effective days means Calendar days minus actual non-effective days......
......this is updated once after each month....value will be encoded....
.....when the month has not yet been consumed....DPM2=RDPM2......

for a sample solution, diregarding other feasible constraints,
::::to solve for the Update Start Date
IF....
sum(M3:U3) = sum of calendar days from Jan to Sep.2006 = 273
sum(M4:U4) = sum of effective days from Jan to Sep.2006 = 245
(average of 3.days per month is deducted as non-effective duration)
AND
orig start date : A5 = 02-OCT-06
THEN
update start date : A7 = A5 + (273-245) = A5 + 28 = 29-OCT-06

::::to solve for the Update Start Date
IF....
sum(M3:V3) = sum of calendar days from Jan to Oct.2006 = 304
sum(M4:V4) = sum of effective days from Jan to Oct.2006 = 273
(average of 3.days per month is deducted as non-effective duration)
AND
orig end date : B5 = 02-NOV-07
THEN
update end date : B7 = B5 + (304-273) = A5 + 31 = 02-DEC-06
::::::
Please take note that we do not have the official daily records, only one
figure in every consumed month.

Thanks in advance for everyone..cheers with excel.....





 
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
sharing excel sheet with multiple users, but other users cant see lana.b Excel Discussion (Misc queries) 3 January 25th 09 11:15 AM
SAS users please help arizona302 Excel Discussion (Misc queries) 0 May 16th 06 05:22 PM
Getting Users Name fastmonkey512[_3_] Excel Programming 3 February 13th 06 08:49 PM
prevent users from overwriting other users data [email protected] Excel Worksheet Functions 0 April 17th 05 08:18 PM
Help - Automating a file.. Adding Users , Deleting users, Changing Tim Harding Excel Worksheet Functions 0 March 16th 05 01:25 PM


All times are GMT +1. The time now is 05:32 AM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"