In my spreadsheet, I have some inspection dates of some materials that I
have. I have to inspect these items on a "julian date" (30-day) interval. For example: A1 -- inspected date is 1 February 2006 (which is a Wednesday) B1 -- Next inspection due date is 30 days from inspected date (may or may not be a Wedensday) I have to inspect this item every 30 days, so I used the formula: (In cell B1) "=A1+30" This gave me 30 days after the inspected date, but I want the inspection to show due on the Wednesday before the 30-day becomes due. Is there a way to tell Excel to defer to the Wednesday immediately before the 30-day inpsection is due? |
Date and Day Programming
=A1+30-CHOOSE(WEEKDAY(A1),6,0,1,2,3,4,5)
-- HTH Bob Phillips (remove nothere from email address if mailing direct) "Gee-off" wrote in message ... In my spreadsheet, I have some inspection dates of some materials that I have. I have to inspect these items on a "julian date" (30-day) interval. For example: A1 -- inspected date is 1 February 2006 (which is a Wednesday) B1 -- Next inspection due date is 30 days from inspected date (may or may not be a Wedensday) I have to inspect this item every 30 days, so I used the formula: (In cell B1) "=A1+30" This gave me 30 days after the inspected date, but I want the inspection to show due on the Wednesday before the 30-day becomes due. Is there a way to tell Excel to defer to the Wednesday immediately before the 30-day inpsection is due? |
Date and Day Programming
Hey thanks Bob for your help. I used that formula in my cell, and it
returned a number of 25. What exactly is this displaying to me? I just don't understand what exactly this formula is accomplishing. Thanks. "Bob Phillips" wrote: =A1+30-CHOOSE(WEEKDAY(A1),6,0,1,2,3,4,5) -- HTH Bob Phillips (remove nothere from email address if mailing direct) "Gee-off" wrote in message ... In my spreadsheet, I have some inspection dates of some materials that I have. I have to inspect these items on a "julian date" (30-day) interval. For example: A1 -- inspected date is 1 February 2006 (which is a Wednesday) B1 -- Next inspection due date is 30 days from inspected date (may or may not be a Wedensday) I have to inspect this item every 30 days, so I used the formula: (In cell B1) "=A1+30" This gave me 30 days after the inspected date, but I want the inspection to show due on the Wednesday before the 30-day becomes due. Is there a way to tell Excel to defer to the Wednesday immediately before the 30-day inpsection is due? |
Date and Day Programming
Bob's formula subtracts a number based on the weekday of your planned
inspection date to calculate the date 28 days after to ensure it falls on a Wednesday. I tried it and it works OK for me. B1 must be formatted as date. "Gee-off" wrote: Hey thanks Bob for your help. I used that formula in my cell, and it returned a number of 25. What exactly is this displaying to me? I just don't understand what exactly this formula is accomplishing. Thanks. "Bob Phillips" wrote: =A1+30-CHOOSE(WEEKDAY(A1),6,0,1,2,3,4,5) -- HTH Bob Phillips (remove nothere from email address if mailing direct) "Gee-off" wrote in message ... In my spreadsheet, I have some inspection dates of some materials that I have. I have to inspect these items on a "julian date" (30-day) interval. For example: A1 -- inspected date is 1 February 2006 (which is a Wednesday) B1 -- Next inspection due date is 30 days from inspected date (may or may not be a Wedensday) I have to inspect this item every 30 days, so I used the formula: (In cell B1) "=A1+30" This gave me 30 days after the inspected date, but I want the inspection to show due on the Wednesday before the 30-day becomes due. Is there a way to tell Excel to defer to the Wednesday immediately before the 30-day inpsection is due? |
Date and Day Programming
thank you very much for the explanation.
"Toppers" wrote: Bob's formula subtracts a number based on the weekday of your planned inspection date to calculate the date 28 days after to ensure it falls on a Wednesday. I tried it and it works OK for me. B1 must be formatted as date. "Gee-off" wrote: Hey thanks Bob for your help. I used that formula in my cell, and it returned a number of 25. What exactly is this displaying to me? I just don't understand what exactly this formula is accomplishing. Thanks. "Bob Phillips" wrote: =A1+30-CHOOSE(WEEKDAY(A1),6,0,1,2,3,4,5) -- HTH Bob Phillips (remove nothere from email address if mailing direct) "Gee-off" wrote in message ... In my spreadsheet, I have some inspection dates of some materials that I have. I have to inspect these items on a "julian date" (30-day) interval. For example: A1 -- inspected date is 1 February 2006 (which is a Wednesday) B1 -- Next inspection due date is 30 days from inspected date (may or may not be a Wedensday) I have to inspect this item every 30 days, so I used the formula: (In cell B1) "=A1+30" This gave me 30 days after the inspected date, but I want the inspection to show due on the Wednesday before the 30-day becomes due. Is there a way to tell Excel to defer to the Wednesday immediately before the 30-day inpsection is due? |