issue with adding weeks to the date
Hi I've got a problem where i have a list of dates, all of which i need to at six weeks to. that bit isn't to tricky, however, some of the dates could be either a saturday or sunday or bank holiday. If thats the case it then needs to add a day or two to the six weeks inorder to get it clear of a 'non working day' Also, if its around christmas, this issue is increased as the bank holidays are next to each other. Has anyone got any ideas on how to do this? theres about 14000 dates so doing it by hand could take a while!!! Thanks Matt :eek: :confused: :eek: -- matthewwookie ------------------------------------------------------------------------ matthewwookie's Profile: http://www.excelforum.com/member.php...o&userid=27503 View this thread: http://www.excelforum.com/showthread...hreadid=473738 |
issue with adding weeks to the date
Take a look at WORKDAY() in XL Help. It's part of the Analysis Toolpak
Addin, so you'll have to ensure that that's loaded (Tools/Addins...) =WORKDAY(A1+41,1,<holidays) In article , matthewwookie wrote: Hi I've got a problem where i have a list of dates, all of which i need to at six weeks to. that bit isn't to tricky, however, some of the dates could be either a saturday or sunday or bank holiday. If thats the case it then needs to add a day or two to the six weeks inorder to get it clear of a 'non working day' Also, if its around christmas, this issue is increased as the bank holidays are next to each other. Has anyone got any ideas on how to do this? theres about 14000 dates so doing it by hand could take a while!!! Thanks Matt :eek: :confused: :eek: |
All times are GMT +1. The time now is 03:42 PM. |
Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com