Putting in dates for three months(From week 1 thur week 16)
|
Dates
Put the first date in A1.
In A2, put =A1+7 copy down as far as is needed. -- HTH Bob Phillips (remove nothere from the email address if mailing direct) "Roy" wrote in message ... Putting in dates for three months(From week 1 thur week 16) |