default days
On excel 2003 i am using networkdays function on that the default was set to
5 days now i want to change it to 6 days. How do i proceed |
default days
Do you mean 6 working days in a week? If so, try
=SUMPRODUCT(INT((MAX(end_date,start_date)-WEEKDAY(MAX(end_date,start_date)+1 -{2;3;4;5;6;7})-MIN(end_date,start_date)+8)/7)) -SUMPRODUCT(ISNUMBER(MATCH(WEEKDAY(holidays),{2;3;4 ;5;6;7},0))*(holidays=MI N(end_date,start_date))*(holidays<=MAX(end_date,st art_date))) This assume Mon-Sat, so just change the array 2;3;4;5;6;7 to 1;2;3;4;5;6 if you want Sun-Fri. -- HTH Bob Phillips (remove nothere from email address if mailing direct) "Avudaiyappan" wrote in message ... On excel 2003 i am using networkdays function on that the default was set to 5 days now i want to change it to 6 days. How do i proceed |