How do I set up a formula on a time sheet to calculate time in 1/.
I am setting up a time spreadsheet and I want all of my totals to be
calculated in 1/4 increments. Example: IN OUT IN OUT TOTAL 7:01 AM 11:47AM 12:50 PM 4:32 PM = 8:30 hours |
Don't know what you total formula is, but let us say it is
=(B2-A2)+(D2-C2) If you want to round this to the nearest quarter hour use =ROUND(((B2-A2)+(D2-C2))*96,0)/96 If you want to round up a quarter hour, use =ROUNDUP(((B2-A2)+(D2-C2))*96,0)/96 -- HTH RP (remove nothere from the email address if mailing direct) "gschmid" wrote in message ... I am setting up a time spreadsheet and I want all of my totals to be calculated in 1/4 increments. Example: IN OUT IN OUT TOTAL 7:01 AM 11:47AM 12:50 PM 4:32 PM = 8:30 hours |
Just another way:
=CEILING(B2-A2+D2-C2, 1/96) In article , "Bob Phillips" wrote: If you want to round up a quarter hour, use =ROUNDUP(((B2-A2)+(D2-C2))*96,0)/96 |
All times are GMT +1. The time now is 11:32 PM. |
Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com