Workday calculation
I want to know how many workdays have pasted. In cell E6 is the first
workday and E7 is the ending Workday. What is the formula to know how many Workdays have pasted? |
Workday calculation
=NETWORKDAYS( Startdate, Enddate, holidays)
I believe that depending on the version number of excel - you may need the analysis toolpack installed edvwvw heater wrote: I want to know how many workdays have pasted. In cell E6 is the first workday and E7 is the ending Workday. What is the formula to know how many Workdays have pasted? -- Message posted via OfficeKB.com http://www.officekb.com/Uwe/Forums.a...excel/200905/1 |