holidays does not work properly in networkdays funtion.
 
I have been trying to use networkdays funtion. When I put in the holiday
dates it does not work with every date I put in.


Example:

putting in 2/6/2009 start date
putting in 12/25/2009 end date
putting in 2/14/2009 Holiday

When I put in the exclusion date (Holiday ) : 2/7/2009 does not work
2/8/2009
does not work
2/9/2009
works
2/10/2009
works
2/11/2009
works
2/12/2009
works
2/13/2009
works
2/14/2009
does not work
2/15/2009
does not work
2/16/2009
does work

I would rather not go through all the dates to find out which ones work and
which ones do not.

I'm using this funtion to make a countdown to Christmas with excluding
weekends and holidays.

I re-installed office and the problem still exists

Has anyone else had this problem?
Does anyone have a explanation and fix on whats happening.



Shane Devenshire[_2_]

holidays does not work properly in networkdays funtion.
 
Hi,

The dates that you say are not working are Weekends! The Networkdays
function excludes those by definition, but not twice.
--
If this helps, please click the Yes button

Cheers,
Shane Devenshire


"GAW" wrote:

I have been trying to use networkdays funtion. When I put in the holiday
dates it does not work with every date I put in.


Example:

putting in 2/6/2009 start date
putting in 12/25/2009 end date
putting in 2/14/2009 Holiday

When I put in the exclusion date (Holiday ) : 2/7/2009 does not work
2/8/2009
does not work
2/9/2009
works
2/10/2009
works
2/11/2009
works
2/12/2009
works
2/13/2009
works
2/14/2009
does not work
2/15/2009
does not work
2/16/2009
does work

I would rather not go through all the dates to find out which ones work and
which ones do not.

I'm using this funtion to make a countdown to Christmas with excluding
weekends and holidays.

I re-installed office and the problem still exists

Has anyone else had this problem?
Does anyone have a explanation and fix on whats happening.



Fred Smith[_4_]

holidays does not work properly in networkdays funtion.
 
February 14th is a Saturday, so will automatically be excluded by
Networkdays.

The function has worked for thousands of people, and it will work for you
too.

Regards,
Fred.

"GAW" wrote in message
...
I have been trying to use networkdays funtion. When I put in the holiday
dates it does not work with every date I put in.


Example:

putting in 2/6/2009 start date
putting in 12/25/2009 end date
putting in 2/14/2009 Holiday

When I put in the exclusion date (Holiday ) : 2/7/2009 does not work
2/8/2009
does not work
2/9/2009
works
2/10/2009
works
2/11/2009
works
2/12/2009
works
2/13/2009
works
2/14/2009
does not work
2/15/2009
does not work
2/16/2009
does work

I would rather not go through all the dates to find out which ones work
and
which ones do not.

I'm using this funtion to make a countdown to Christmas with excluding
weekends and holidays.

I re-installed office and the problem still exists

Has anyone else had this problem?
Does anyone have a explanation and fix on whats happening.




JE McGimpsey

holidays does not work properly in networkdays funtion.
 
What do you mean when you say "doesn't work".

A holiday of 2/7 doesn't affect the calculation since 2/7 is a Saturday,
which is already excluded. As is 2/8.



In article ,
GAW wrote:

I have been trying to use networkdays funtion. When I put in the holiday
dates it does not work with every date I put in.


Example:

putting in 2/6/2009 start date
putting in 12/25/2009 end date
putting in 2/14/2009 Holiday

When I put in the exclusion date (Holiday ) : 2/7/2009 does not work
2/8/2009
does not work
2/9/2009
works
2/10/2009
works
2/11/2009
works
2/12/2009
works
2/13/2009
works
2/14/2009
does not work
2/15/2009
does not work
2/16/2009
does work

I would rather not go through all the dates to find out which ones work and
which ones do not.

I'm using this funtion to make a countdown to Christmas with excluding
weekends and holidays.

I re-installed office and the problem still exists

Has anyone else had this problem?
Does anyone have a explanation and fix on whats happening.



GAW

holidays does not work properly in networkdays funtion.
 


"Shane Devenshire" wrote:

Hi,

The dates that you say are not working are Weekends! The Networkdays
function excludes those by definition, but not twice.
--
If this helps, please click the Yes button

Cheers,
Shane Devenshire


"GAW" wrote:

I have been trying to use networkdays funtion. When I put in the holiday
dates it does not work with every date I put in.


Example:

putting in 2/6/2009 start date
putting in 12/25/2009 end date
putting in 2/14/2009 Holiday

When I put in the exclusion date (Holiday ) : 2/7/2009 does not work
2/8/2009
does not work
2/9/2009
works
2/10/2009
works
2/11/2009
works
2/12/2009
works
2/13/2009
works
2/14/2009
does not work
2/15/2009
does not work
2/16/2009
does work

I would rather not go through all the dates to find out which ones work and
which ones do not.

I'm using this funtion to make a countdown to Christmas with excluding
weekends and holidays.

I re-installed office and the problem still exists

Has anyone else had this problem?
Does anyone have a explanation and fix on whats happening.

Thanks for the help guys. I didn't realize that it did not count the weekends......again thanks



All times are GMT +1. The time now is 01:08 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com