Totti

how to get "EndDate" of a project?
 
Hi all,
I am wondering how can I get the end date of a project if i have the
starting date, the workdays that it will need, the fact that a week
have 5 working days and a list of hollydays?

the problem is that in B:B i have many projects each starting in a
different date, some in 2008 some in 2009, i imported to C:C the
working days. Now in D:D and i have the hollydays in format "dd-mm"
independent of the year, so now what should i do to get the end day?
including the weekends and if any date from the hollydays, happen to
be after the starting date of the project and automatically get the
end date. which will therefore be, StartDay+HollyDays+WeekEnd
+WorkDays, all these add up together to the EndDay.

sample data:

Start date Work days
05.21.2008 9
11.05.2008 124
12.28.2008 35
02.07.2009 114


and the hollydays are in the form DD - MM (year - independant)


DD MM
12 01
11 02
3 03
25 04
22 07
1 09
2 11
21 11
31 12


How should i approach such a problem?

Thanks

JE McGimpsey

how to get "EndDate" of a project?
 
See Help for the WORKDAY() function.

For holidays, I would combine them into one cell per holiday, rather
than monht/day.

In article
,
Totti wrote:

Hi all,
I am wondering how can I get the end date of a project if i have the
starting date, the workdays that it will need, the fact that a week
have 5 working days and a list of hollydays?

the problem is that in B:B i have many projects each starting in a
different date, some in 2008 some in 2009, i imported to C:C the
working days. Now in D:D and i have the hollydays in format "dd-mm"
independent of the year, so now what should i do to get the end day?
including the weekends and if any date from the hollydays, happen to
be after the starting date of the project and automatically get the
end date. which will therefore be, StartDay+HollyDays+WeekEnd
+WorkDays, all these add up together to the EndDay.

sample data:

Start date Work days
05.21.2008 9
11.05.2008 124
12.28.2008 35
02.07.2009 114


and the hollydays are in the form DD - MM (year - independant)


DD MM
12 01
11 02
3 03
25 04
22 07
1 09
2 11
21 11
31 12


How should i approach such a problem?

Thanks


Totti

how to get "EndDate" of a project?
 
I finally came up with this solution:
={WORKDAY(A2,B2,(DATE(YEAR(A2),$K$20:$K$28,$J$20:$ J$28)))}
whe
A2 = Starting Date
B2 = Number of working days
$K$20:$K$28 = Array of Months
$J$20:$J$28 = Array od Days

so i tried to make a virtual array generating the date from the year
of the cell, days and months(of holidays) provided by the user and
copied it down through the starting days of the projects.
I am not sure if this is OK, so I need your thougths please.