Cam

How to calculate between two date/time fields?
 
Hello,

How do I calculate the time in hours or days between two fields (startDate
and FinishDate in Date/Time format 8/12/2008 14:41) less weekend and holiday?

Example:
StartDate FinishDate Result
8/12/2008 12:09 8/12/2008 14:41 92 mins or 1.53 hrs or 0.936
days

Thanks





smartin

How to calculate between two date/time fields?
 
Cam wrote:
Hello,

How do I calculate the time in hours or days between two fields (startDate
and FinishDate in Date/Time format 8/12/2008 14:41) less weekend and holiday?

Example:
StartDate FinishDate Result
8/12/2008 12:09 8/12/2008 14:41 92 mins or 1.53 hrs or 0.936
days

Thanks


Hi Cam,

Chip Pearson has some good info on this:

http://www.cpearson.com/excel/holidays.htm