Dates
I developing a small project plan in excel - starting with project end date
and subtracting task durations to get to start date. Using =DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29) to get to the next earlier date. Problem is I need to exclude weekend dates. D30=end date. C29=duration of task. How do I do that? |
Dates
=WORKDAY(DATE(YEAR(D30),MONTH(D30),DAY(D30)),-C29)
however if you have a date in D30 you don't need the DATE function =D30-C29 or =WORKDAY(D30,-C29) -- Regards, Peo Sjoblom "sharonn" wrote in message ... I developing a small project plan in excel - starting with project end date and subtracting task durations to get to start date. Using =DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29) to get to the next earlier date. Problem is I need to exclude weekend dates. D30=end date. C29=duration of task. How do I do that? |
Dates
I already tried both of these
=workday(E24,D23) results in #NAME? and =workDAY(DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29)) results in #NAME? what am I doing wrong? thx "Peo Sjoblom" wrote: =WORKDAY(DATE(YEAR(D30),MONTH(D30),DAY(D30)),-C29) however if you have a date in D30 you don't need the DATE function =D30-C29 or =WORKDAY(D30,-C29) -- Regards, Peo Sjoblom "sharonn" wrote in message ... I developing a small project plan in excel - starting with project end date and subtracting task durations to get to start date. Using =DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29) to get to the next earlier date. Problem is I need to exclude weekend dates. D30=end date. C29=duration of task. How do I do that? |
Dates
Toolsadd-ins, select ATP (Analysis Toolpak)
and keep the installation CD handy. It comes with Excel but might not be installed at first time, if it is a company PC ask IT to install it if it doesn't install when you check under add-ins -- Regards, Peo Sjoblom "sharonn" wrote in message ... I already tried both of these =workday(E24,D23) results in #NAME? and =workDAY(DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29)) results in #NAME? what am I doing wrong? thx "Peo Sjoblom" wrote: =WORKDAY(DATE(YEAR(D30),MONTH(D30),DAY(D30)),-C29) however if you have a date in D30 you don't need the DATE function =D30-C29 or =WORKDAY(D30,-C29) -- Regards, Peo Sjoblom "sharonn" wrote in message ... I developing a small project plan in excel - starting with project end date and subtracting task durations to get to start date. Using =DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29) to get to the next earlier date. Problem is I need to exclude weekend dates. D30=end date. C29=duration of task. How do I do that? |
Dates
What you are doing wrong is not using Excel help for the WORKDAY function.
-- David Biddulph "sharonn" wrote in message ... I already tried both of these =workday(E24,D23) results in #NAME? and =workDAY(DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29)) results in #NAME? what am I doing wrong? thx "Peo Sjoblom" wrote: =WORKDAY(DATE(YEAR(D30),MONTH(D30),DAY(D30)),-C29) however if you have a date in D30 you don't need the DATE function =D30-C29 or =WORKDAY(D30,-C29) -- Regards, Peo Sjoblom "sharonn" wrote in message ... I developing a small project plan in excel - starting with project end date and subtracting task durations to get to start date. Using =DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29) to get to the next earlier date. Problem is I need to exclude weekend dates. D30=end date. C29=duration of task. How do I do that? |
Dates
Perfect - thank you!
"Peo Sjoblom" wrote: Toolsadd-ins, select ATP (Analysis Toolpak) and keep the installation CD handy. It comes with Excel but might not be installed at first time, if it is a company PC ask IT to install it if it doesn't install when you check under add-ins -- Regards, Peo Sjoblom "sharonn" wrote in message ... I already tried both of these =workday(E24,D23) results in #NAME? and =workDAY(DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29)) results in #NAME? what am I doing wrong? thx "Peo Sjoblom" wrote: =WORKDAY(DATE(YEAR(D30),MONTH(D30),DAY(D30)),-C29) however if you have a date in D30 you don't need the DATE function =D30-C29 or =WORKDAY(D30,-C29) -- Regards, Peo Sjoblom "sharonn" wrote in message ... I developing a small project plan in excel - starting with project end date and subtracting task durations to get to start date. Using =DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29) to get to the next earlier date. Problem is I need to exclude weekend dates. D30=end date. C29=duration of task. How do I do that? |
All times are GMT +1. The time now is 09:44 AM. |
Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com