ExcelBanter

ExcelBanter (https://www.excelbanter.com/)
-   Excel Discussion (Misc queries) (https://www.excelbanter.com/excel-discussion-misc-queries/)
-   -   Tracking Project Progress using Conditional Formatting (https://www.excelbanter.com/excel-discussion-misc-queries/196591-tracking-project-progress-using-conditional-formatting.html)

mickey

Tracking Project Progress using Conditional Formatting
 
I may have been asked to do the impossible, but I know if anyone can help,
someone from this group can.

I need to develop a worksheet to track the weekly progress of several
projects against their due dates. I thought it would be simple using the
TODAY function and conditional formatting--an orange bar for due within 10
days, red for past due, etc.

However, since they want it to update automatically, this means I have to
take into account the week as well as the date--i.e., if I leave my
calculation as it is and the due date is August 10, there will be an orange
bar from the current week through the end of the year. So I need a way to
figure in the current week and have the calculation kick in weekly.

Is this possible? And if so, is there a way to kick OFF the formatting for
the remaining weeks once a project is completed?

Thanks in advance for any suggestions!

--
Mickey


Kevin B

Tracking Project Progress using Conditional Formatting
 
See if this might be of some help:

http://pubs.logicalexpressions.com/p...cle.asp?ID=343

If not, I would google "gantt chart Excel add in" and find a utility that
will do that type of charting. Many of them are free while others can be
purchased for a nominal fee.

Hope this helps.
--
Kevin Backmann


"Mickey" wrote:

I may have been asked to do the impossible, but I know if anyone can help,
someone from this group can.

I need to develop a worksheet to track the weekly progress of several
projects against their due dates. I thought it would be simple using the
TODAY function and conditional formatting--an orange bar for due within 10
days, red for past due, etc.

However, since they want it to update automatically, this means I have to
take into account the week as well as the date--i.e., if I leave my
calculation as it is and the due date is August 10, there will be an orange
bar from the current week through the end of the year. So I need a way to
figure in the current week and have the calculation kick in weekly.

Is this possible? And if so, is there a way to kick OFF the formatting for
the remaining weeks once a project is completed?

Thanks in advance for any suggestions!

--
Mickey


mickey

Tracking Project Progress using Conditional Formatting
 
Kevin, thanks so much. I apologize for the delay in getting back to thank
you--my computer wouldn't go back to the site for some reason.
--
Mickey


"Kevin B" wrote:

See if this might be of some help:

http://pubs.logicalexpressions.com/p...cle.asp?ID=343

If not, I would google "gantt chart Excel add in" and find a utility that
will do that type of charting. Many of them are free while others can be
purchased for a nominal fee.

Hope this helps.
--
Kevin Backmann


"Mickey" wrote:

I may have been asked to do the impossible, but I know if anyone can help,
someone from this group can.

I need to develop a worksheet to track the weekly progress of several
projects against their due dates. I thought it would be simple using the
TODAY function and conditional formatting--an orange bar for due within 10
days, red for past due, etc.

However, since they want it to update automatically, this means I have to
take into account the week as well as the date--i.e., if I leave my
calculation as it is and the due date is August 10, there will be an orange
bar from the current week through the end of the year. So I need a way to
figure in the current week and have the calculation kick in weekly.

Is this possible? And if so, is there a way to kick OFF the formatting for
the remaining weeks once a project is completed?

Thanks in advance for any suggestions!

--
Mickey



All times are GMT +1. The time now is 06:42 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com