Formuals
Code Number Status Last Name Arrival DateDeparture Date
ZAMY 1002 Placed Zulu 5/31/2008 XXXXXXX ZAMY 1038 Placed Silwamba 5/15/2008 8/10/2008 ZAMY 1063 Placed Musopelo 6/6/2008 8/19/2008 Where the XXXXXX is located. I need to take the date in Arrival Date and add 84 days to the 5/31/2008 . PLEASE I am despert.... |
Formuals
With your 5/31/2008 in E1, enter in F1:
=E1+83 this will display 8/22/2008 -- Gary''s Student - gsnu200782 "Gene McKinney YMCA international" wrote: Code Number Status Last Name Arrival DateDeparture Date ZAMY 1002 Placed Zulu 5/31/2008 XXXXXXX ZAMY 1038 Placed Silwamba 5/15/2008 8/10/2008 ZAMY 1063 Placed Musopelo 6/6/2008 8/19/2008 Where the XXXXXX is located. I need to take the date in Arrival Date and add 84 days to the 5/31/2008 . PLEASE I am despert.... |
Formuals
assuming 5/31/2008 is in e1
use =e1+84 hth -- regards from Brazil Thanks in advance for your feedback. Marcelo "Gene McKinney YMCA international" escreveu: Code Number Status Last Name Arrival DateDeparture Date ZAMY 1002 Placed Zulu 5/31/2008 XXXXXXX ZAMY 1038 Placed Silwamba 5/15/2008 8/10/2008 ZAMY 1063 Placed Musopelo 6/6/2008 8/19/2008 Where the XXXXXX is located. I need to take the date in Arrival Date and add 84 days to the 5/31/2008 . PLEASE I am despert.... |
All times are GMT +1. The time now is 05:01 PM. |
Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com