Richard

Completion date
 
L1 = Hours worked per day
G:G = Total time in hours
L2 = Completion date
How would you write this formula to return a completion date?
Thanks in advance!!


Pete_UK

Completion date
 
You will need a start date in order to evaluate the completion date.
Essentially:

= start_date + total_time / hrs_per_day

Hope this helps.