Computing Time from One Day to Another
I need to find the length of time it takes a process to be completed from
start to finish. But its based on a an eight hour work day. For example: Starts on 07/25/07 at 8:00 am finishes at 9:00 am on 07/27/07. I am scheudled to work form 8 to 4 each day. How many minutes did it take to complete -- Thank You, Wendy |
Computing Time from One Day to Another
Try:
=((C1-A1)*8+(D1-B1)*24)*60 Format as general A1=Start Date B1=Start Time C1=Finish Date D1=Finish time HTH "Wendy" wrote: I need to find the length of time it takes a process to be completed from start to finish. But its based on a an eight hour work day. For example: Starts on 07/25/07 at 8:00 am finishes at 9:00 am on 07/27/07. I am scheudled to work form 8 to 4 each day. How many minutes did it take to complete -- Thank You, Wendy |