![]() |
6 day work week
how do you calc a 6 day work week
|
6 day work week
More clarification required, do you want to calculate working days between
two dates based on a 6 day work week, or project a future date based on number of working days added, or something else? Do you want to take holidays into account? "tkirchoff10" wrote: how do you calc a 6 day work week |
6 day work week
Thanks ..Both
1.calculate working days between two dates based on a 6 day work week, 2. project a future date based on a 6 working daysfor your help. Thanks for your help "daddylonglegs" wrote: More clarification required, do you want to calculate working days between two dates based on a 6 day work week, or project a future date based on number of working days added, or something else? Do you want to take holidays into account? "tkirchoff10" wrote: how do you calc a 6 day work week |
6 day work week
Thanks
I need both 1. calculate working days between two dates based on a 6 day work week 2. project a future date based on 6 working days..no Holidays Thanks for your help "daddylonglegs" wrote: More clarification required, do you want to calculate working days between two dates based on a 6 day work week, or project a future date based on number of working days added, or something else? Do you want to take holidays into account? "tkirchoff10" wrote: how do you calc a 6 day work week |
6 day work week
Let's say 6 day work week (Mon-Sat)
Assuming A1 is your start date A2 is your end date A3 =SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)))={2,3,4,5,6,7})) "tkirchoff10" wrote: how do you calc a 6 day work week |
6 day work week
=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)))={2,3,4,5,6,7}))
=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)))1)) =SUM(INT((WEEKDAY(A1-{1,2,3,4,5,6},2)+A2-A1)/7)) Biff "Teethless mama" wrote in message ... Let's say 6 day work week (Mon-Sat) Assuming A1 is your start date A2 is your end date A3 =SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)))={2,3,4,5,6,7})) "tkirchoff10" wrote: how do you calc a 6 day work week |
6 day work week
To project a future date based on start date in A1 and number of days to add
in B1 and assuming a 6 day week (Monday to Saturday) =A1-WEEKDAY(A1,3)+INT(7/6*(B1+MIN(5,WEEKDAY(A1,3)))) "T. Valko" wrote: =SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)))={2,3,4,5,6,7})) =SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)))1)) =SUM(INT((WEEKDAY(A1-{1,2,3,4,5,6},2)+A2-A1)/7)) Biff "Teethless mama" wrote in message ... Let's say 6 day work week (Mon-Sat) Assuming A1 is your start date A2 is your end date A3 =SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)))={2,3,4,5,6,7})) "tkirchoff10" wrote: how do you calc a 6 day work week |
6 day work week
Thank u sir,
the foll formula gives good results, =A1-WEEKDAY(A1,3)+INT(7/6*(B1+MIN(5,WEEKDAY(A1,3)))) can u tell me were can i fit holidays or list of holidays in above formula to exclude holidays from the calculation. thanks, EggHeadCafe.com - .NET Developer Portal of Choice http://www.eggheadcafe.com |
1 Attachment(s)
I created this with a 5 work week and a 6 work week table.
To include the holidays, just simply populate it with the dates (as formatted in the example) in the Holidays Tab (formula is until Row 20). |
All times are GMT +1. The time now is 04:47 PM. |
Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com