i am trying to set up a series of dates in cells that will show four days
consecutively and then skip the next four days and run in a continual pattern for the entire year. for example: i want the first four cells to read 1/1/05, 1/2/05, 1/3/05, 1/4/05 and the next four to read 1/9/05, 1/10/05, 1/11/05, 1/12/05 and so on. can anyone help? |
Assuming the first date is in A3, put this formula in A4:
=IF(MOD(ROW(),4)=MOD(ROW($A$3),4),A3+5,A3+1) The $A$3 must refer to the cell containing the first date. On Thu, 3 Feb 2005 15:29:07 -0800, "tpapd754" wrote: i am trying to set up a series of dates in cells that will show four days consecutively and then skip the next four days and run in a continual pattern for the entire year. for example: i want the first four cells to read 1/1/05, 1/2/05, 1/3/05, 1/4/05 and the next four to read 1/9/05, 1/10/05, 1/11/05, 1/12/05 and so on. can anyone help? |
All times are GMT +1. The time now is 07:33 PM. |
Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com