In a GANTT, how do I get diff projects to start later on chart
I want to show a flow of projects, by date. When one stops, the other starts
or maybe the next starts a couple days before. How do you set up the GANTT to show the stepping effect. Currently all I can get it to do is all projects start at the same time. Thanks for the help |
A project bar in a Gantt chart is the stacked bar defined by a start date and a
duration. To make a bar start later, give it a later start date. You should be able to use formulas to relate a later start to the earlier starting date and duration of another bar. These articles might be of assistance: http://pubs.logicalexpressions.com/P...cle.asp?ID=343 http://peltiertech.com/Excel/Charts/GanttChart.html - Jon ------- Jon Peltier, Microsoft Excel MVP Peltier Technical Services Tutorials and Custom Solutions http://PeltierTech.com/ _______ Tim wrote: I want to show a flow of projects, by date. When one stops, the other starts or maybe the next starts a couple days before. How do you set up the GANTT to show the stepping effect. Currently all I can get it to do is all projects start at the same time. Thanks for the help |
All times are GMT +1. The time now is 11:55 AM. |
Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com