ok so there are loads of Gantt charts out there that use days completed and
days left and only a start date....I would like to use % completed and remaing using an end date - does anyone know how to do this? Task description Start date End date % completed % remaining. |
Gantt Chart!
Use a formula to translate % complete into days complete:
=(EndDate - StartDate) * % Complete DaysLeft: =EndDate - DaysComplete -- Best Regards, Luke M "Scott_goddard" wrote in message ... ok so there are loads of Gantt charts out there that use days completed and days left and only a start date....I would like to use % completed and remaing using an end date - does anyone know how to do this? Task description Start date End date % completed % remaining. |