Switch X & Y axis' when both data columns are dates (target/actual
I am plotting Target vs Actual completion dates for a project management
S-Curve, using Excel. Since both data columns are "dates", Excel wants to use "dates" on the Value Axis (Y), while putting the Task #s on the X axis. How do I switch axis' so that time runs horizontally on the X axis, with the Task #s on the Y? Thanks |
Switch X & Y axis' when both data columns are dates (target/actual
Chart menu Source Data Series tab: change what's in the edit boxes for X
and Y. You could try this utility: http://peltiertech.com/Excel/Charts/axes.html#SwitchXY - Jon ------- Jon Peltier, Microsoft Excel MVP Tutorials and Custom Solutions Peltier Technical Services, Inc. - http://PeltierTech.com _______ "Petez2" wrote in message ... I am plotting Target vs Actual completion dates for a project management S-Curve, using Excel. Since both data columns are "dates", Excel wants to use "dates" on the Value Axis (Y), while putting the Task #s on the X axis. How do I switch axis' so that time runs horizontally on the X axis, with the Task #s on the Y? Thanks |
All times are GMT +1. The time now is 08:49 AM. |
Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com