Task name Start Date Complete Remaining Start date % complete
Locations 27/11/2006 8.8 2.2 8/12/2006 80

In complete cell this formula is used =IF((I8-E8)*J8/100=0,0,(I8-E8)*J8/100)
In Remaining cell this formula is used =IF((I8-E8)-F8=0,"",(I8-E8)-F8)

My question is, what do these formula show? Complete / Remaining what?
Days? Percentage? If its days greats thats what I need and only working
days.

Please help ASAP





 
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Circular Reference Forumlas acebrown Excel Discussion (Misc queries) 1 July 22nd 06 02:47 AM
Conditional Formats - Forumlas VBA Noob Excel Worksheet Functions 6 July 20th 06 10:57 PM
Forumlas Not Executing Trey Excel Discussion (Misc queries) 2 January 25th 06 04:02 PM
Selecetive replication of forumlas brodiemac Excel Discussion (Misc queries) 4 August 11th 05 08:07 PM
Help with Commission forumlas asdfasdf Excel Worksheet Functions 6 November 15th 04 05:28 PM


All times are GMT +1. The time now is 10:41 AM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"