Thanks David - tried that one - it changes the cell to "Open Call" for some
reason?

"David Biddulph" wrote:

Have you looked at NETWORKDAYS(), rather than DAYS360() ?
--
David Biddulph

"Andy B" wrote in message
...
I am trying to calculate the difference between one cell and another - both
having dates in, to establish if a service level is being achieved for
completing a task.

eg. B2 = 25/6/07 and L2 = 30/6/07 (5 days)

currently if there is no date in L2, it will say "open call" - indicating
that it has not been completed.

the calculation used currently is =IF(ISERROR(DAYS360(B2,L2,TRUE)),"Open
Call",DAYS360(B2,L2,TRUE)) however this does not show working days taken
to
complete the call, which is key to the measurement.

Can anybody help please?




  #2   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 8,651
Default calculating a formula for a service level

I can't guess what your problem is unless you tell us the formula you're
using and what the values are in the relevant cells. Are you sure you've
got real dates and not text values? What value does =L2-B2 (or whatever the
relevant cells are) give? And if you are getting an error flagged by
ISERROR(), then you need to look at what specific error the formula inside
the function gives.
--
David Biddulph

"Andy B" wrote in message
...
Thanks David - tried that one - it changes the cell to "Open Call" for
some
reason?


"David Biddulph" wrote:

Have you looked at NETWORKDAYS(), rather than DAYS360() ?


"Andy B" wrote in message
...
I am trying to calculate the difference between one cell and another -
both
having dates in, to establish if a service level is being achieved for
completing a task.

eg. B2 = 25/6/07 and L2 = 30/6/07 (5 days)

currently if there is no date in L2, it will say "open call" -
indicating
that it has not been completed.

the calculation used currently is
=IF(ISERROR(DAYS360(B2,L2,TRUE)),"Open
Call",DAYS360(B2,L2,TRUE)) however this does not show working days
taken
to
complete the call, which is key to the measurement.

Can anybody help please?






Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Calculate SLA ( Service Level Agreement ). Thyag Excel Worksheet Functions 2 April 5th 23 01:18 PM
calculating a formula for a service level Andy B Excel Worksheet Functions 1 August 2nd 07 12:20 PM
formula for calculating 401k if over or equal to 1 yr of service . thomas Excel Worksheet Functions 1 March 24th 05 06:43 AM
calculating service dates Tanya Excel Worksheet Functions 2 January 3rd 05 09:15 PM
Help with Years of Service formula.... Wild Bill Excel Discussion (Misc queries) 1 December 6th 04 09:47 PM


All times are GMT +1. The time now is 08:14 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"