need scenarios function to running MPS for production planning
Example : week 5, customer ABC's requirement is 100,000 pcs of 1U, 30,000 pcs of 1T, 60,000 pcs of PP, 1,000 pcs of 2T and 1,000 pcs of 1C. Under such scenarios, my company have 5 production lines as follows :- Line 1 : only can run 1U and PP (total added up to 100%) Line 2 : only can run 1U and PP (total added up to 100%) Line 3 : only can run 1C, 1T and 2T (total added up to 100%) Line 4 : only can run 1U and PP (total added up to 100%) Line 5 : can run 1C, 1T, 2T, 1U and PP (total added up to 100%) i tried Goal Seek in MS. Excel but it doesn't work with some many scenarios at the same time ... so can anyone help to advice me a shortest way to get this done ? currently, i m manualling joggaling using excel spreadsheet ... it is very time consuming ... -- jl |
#2
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
need scenarios function to running MPS for production planning
Dear jl,
Since you have many constraints, it's better use "solver" than "goal seek" to your satisfaction. Regards, ll jl wrote: Example : week 5, customer ABC's requirement is 100,000 pcs of 1U, 30,000 pcs of 1T, 60,000 pcs of PP, 1,000 pcs of 2T and 1,000 pcs of 1C. Under such scenarios, my company have 5 production lines as follows :- Line 1 : only can run 1U and PP (total added up to 100%) Line 2 : only can run 1U and PP (total added up to 100%) Line 3 : only can run 1C, 1T and 2T (total added up to 100%) Line 4 : only can run 1U and PP (total added up to 100%) Line 5 : can run 1C, 1T, 2T, 1U and PP (total added up to 100%) i tried Goal Seek in MS. Excel but it doesn't work with some many scenarios at the same time ... so can anyone help to advice me a shortest way to get this done ? currently, i m manualling joggaling using excel spreadsheet ... it is very time consuming ... -- jl |
#3
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
need scenarios function to running MPS for production planning
hi ll, Thanks ... do you have any ideas how does a solver works on my scenarios ... Will highly appreciate if you could give me an example ... that will be great... -- jl " wrote: Dear jl, Since you have many constraints, it's better use "solver" than "goal seek" to your satisfaction. Regards, ll jl wrote: Example : week 5, customer ABC's requirement is 100,000 pcs of 1U, 30,000 pcs of 1T, 60,000 pcs of PP, 1,000 pcs of 2T and 1,000 pcs of 1C. Under such scenarios, my company have 5 production lines as follows :- Line 1 : only can run 1U and PP (total added up to 100%) Line 2 : only can run 1U and PP (total added up to 100%) Line 3 : only can run 1C, 1T and 2T (total added up to 100%) Line 4 : only can run 1U and PP (total added up to 100%) Line 5 : can run 1C, 1T, 2T, 1U and PP (total added up to 100%) i tried Goal Seek in MS. Excel but it doesn't work with some many scenarios at the same time ... so can anyone help to advice me a shortest way to get this done ? currently, i m manualling joggaling using excel spreadsheet ... it is very time consuming ... -- jl |
#4
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
need scenarios function to running MPS for production planning
jl -
Excel models for Machine Allocation problems are available at http://www.solver.com/proframe.htm Your problem statement is not complete. You need details of unit capacity for each line, details of cost, etc. - Mike http://mikemiddleton.com "jl" wrote in message ... hi ll, Thanks ... do you have any ideas how does a solver works on my scenarios ... Will highly appreciate if you could give me an example ... that will be great... -- jl " wrote: Dear jl, Since you have many constraints, it's better use "solver" than "goal seek" to your satisfaction. Regards, ll jl wrote: Example : week 5, customer ABC's requirement is 100,000 pcs of 1U, 30,000 pcs of 1T, 60,000 pcs of PP, 1,000 pcs of 2T and 1,000 pcs of 1C. Under such scenarios, my company have 5 production lines as follows :- Line 1 : only can run 1U and PP (total added up to 100%) Line 2 : only can run 1U and PP (total added up to 100%) Line 3 : only can run 1C, 1T and 2T (total added up to 100%) Line 4 : only can run 1U and PP (total added up to 100%) Line 5 : can run 1C, 1T, 2T, 1U and PP (total added up to 100%) i tried Goal Seek in MS. Excel but it doesn't work with some many scenarios at the same time ... so can anyone help to advice me a shortest way to get this done ? currently, i m manualling joggaling using excel spreadsheet ... it is very time consuming ... -- jl |
#5
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
need scenarios function to running MPS for production planning
Dear jl,
The office suite has a sample demonstrating how to use solver function. Use the search "solvsamp.xls" in your computer. ll jl wrote: hi ll, Thanks ... do you have any ideas how does a solver works on my scenarios ... Will highly appreciate if you could give me an example ... that will be great... -- jl " wrote: Dear jl, Since you have many constraints, it's better use "solver" than "goal seek" to your satisfaction. Regards, ll jl wrote: Example : week 5, customer ABC's requirement is 100,000 pcs of 1U, 30,000 pcs of 1T, 60,000 pcs of PP, 1,000 pcs of 2T and 1,000 pcs of 1C. Under such scenarios, my company have 5 production lines as follows :- Line 1 : only can run 1U and PP (total added up to 100%) Line 2 : only can run 1U and PP (total added up to 100%) Line 3 : only can run 1C, 1T and 2T (total added up to 100%) Line 4 : only can run 1U and PP (total added up to 100%) Line 5 : can run 1C, 1T, 2T, 1U and PP (total added up to 100%) i tried Goal Seek in MS. Excel but it doesn't work with some many scenarios at the same time ... so can anyone help to advice me a shortest way to get this done ? currently, i m manualling joggaling using excel spreadsheet ... it is very time consuming ... -- jl |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
Fill Function to next Column | Excel Worksheet Functions | |||
clock | Excel Worksheet Functions | |||
Need a ISWorkday Function -- Any Ideas | Excel Worksheet Functions | |||
Conversion | Excel Worksheet Functions | |||
HOW CAN I GET OFFICE 2003 EXCEL BASIC TO NEST FUNCTIONS LIKE EXCE. | Excel Worksheet Functions |